8602 S DENVER AVE 90044
Certificate Information: 8602 S DENVER AVE 90044
- Application / Permit
- 23010-10000-01881
- Plan Check / Job No.
- B23LA08281
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ePlan: New 9'x18' pre-fabricated unmanned equipment enclosure.
- Permit Issued
- Issued on 4/17/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2023 | PINANK PATEL |
| Corrections Issued | 5/24/2023 | PINANK PATEL |
| Applicant returned to address corrections | 4/5/2024 | PINANK PATEL |
| Plan Check Approved | 4/10/2024 | PINANK PATEL |
| Issued | 4/17/2024 | APPLICANT |
| Permit Finaled | 6/20/2025 | RAFAEL ESPINOZA |
| CofO Issued | 6/20/2025 | RAFAEL ESPINOZA |
| Permit Finaled | 6/20/2025 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 6/15/2023 | TREVOR QUAN |
| Community Plan Implem. Overlay | Cleared | 6/20/2023 | OSCAR CASTRO |
| Community Plan Implem. Overlay | Cleared | 6/26/2023 | JIMMY VIVAR |
| Community Plan Implem. Overlay | Cleared | 2/28/2024 | MANERI ROMAN |
| Community Plan Implem. Overlay | Cleared | 2/29/2024 | DYNL MIRANDA |
| Specific Plan | Cleared | 3/1/2024 | RYAN LY |
| ZI | Cleared | 3/1/2024 | RYAN LY |
| ZI | Cleared | 3/1/2024 | RYAN LY |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2024 | TREVOR QUAN |
| Redevelopment Project Area | Cleared | 3/11/2024 | YASMINE BASHIRI |
| ZI | Cleared | 3/11/2024 | YASMINE BASHIRI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burrows,, Rodney Dale; Lic. No.: C39437 | 1330 NICKEL COURT BROOMFIELD, CO 80020 |
| Engineer | Montoya,, Hernan; Lic. No.: S2819 | , |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/10/2024 | Approved | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 8/29/2024 | Approved | JAMES POWERS |
| Final | 2/3/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 2/3/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Verify Sprinkler Sign Off | 2/3/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 2/3/2025 | Partial Approval | ALFREDO LOPEZ |
| Final | 4/28/2025 | Partial Approval | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 4/28/2025 | SGSOV No Gas | RAFAEL ESPINOZA |
| Smoke Detectors | 4/28/2025 | Approved | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 4/28/2025 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 4/28/2025 | Approved | RAFAEL ESPINOZA |
| Final | 6/4/2025 | Partial Inspection | RAFAEL ESPINOZA |