16180 W MULHOLLAND DR 90049

Certificate Information: 16180 W MULHOLLAND DR 90049

Application / Permit
23010-10000-01879
Plan Check / Job No.
B23LA08275
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Patio Cover
Work Description
<ePlan> New 21'4" X 50'0" detached shade canopy in courtyard adjacent to classrooms PER CPC-2017-4219-VCU-SPE-DRB-SPP-MSP
Permit Issued
Issued on 6/13/2024
Issuing Office
Current Status
CofO Issued on 2/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 MARVEL DELACRUZ
Corrections Issued 5/14/2023 MARVEL DELACRUZ
Quality Review Completed 5/18/2023 OMID HEDAYAT
Applicant returned to address corrections 6/1/2023 MARVEL DELACRUZ
Applicant returned to address corrections 8/23/2023 MARVEL DELACRUZ
Applicant returned to address corrections 4/22/2024 MARVEL DELACRUZ
Applicant returned to address corrections 4/23/2024 MARVEL DELACRUZ
Applicant returned to address corrections 5/31/2024 MARVEL DELACRUZ
Applicant returned to address corrections 6/5/2024 MARVEL DELACRUZ
Plan Check Approved 6/7/2024 MARVEL DELACRUZ
Issued 6/13/2024 APPLICANT
Permit Finaled 2/25/2025 HENRY BAGHDASSARIAN
Permit Finaled 2/25/2025 HENRY BAGHDASSARIAN
CofO Issued 2/25/2025 HENRY BAGHDASSARIAN

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/1/2023 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 6/1/2023 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 6/1/2023 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 6/1/2023 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 6/1/2023 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 6/1/2023 ANTHONY MAINEZ
Distance to fire station Cleared 8/10/2023 MATTHEW CRAIG
Hydrant and Access approval Cleared 8/10/2023 MATTHEW CRAIG
Low Impact Development (LID) Cleared 9/8/2023 MARTIN FRAGOSO
Grading Pre-Inspection Cleared 9/13/2023 ALEXANDER HELFER
Miscellaneous Cleared 9/20/2023 JASON CHAN
Miscellaneous Cleared 9/20/2023 JASON CHAN
Miscellaneous Cleared 9/20/2023 JASON CHAN
Miscellaneous Cleared 9/20/2023 JASON CHAN
Specific Plan Cleared 9/20/2023 JASON CHAN
ZI Cleared 9/20/2023 JASON CHAN
Roof/Waste drainage to street Cleared 1/30/2024 BRENDEN HAWK
Fire Marshal Fire Life Safety Cleared 3/20/2024 MENOA AGHAJANI
GPI Written Notices Cleared 6/3/2024 MARVEL DELACRUZ

Contact Information

Architect Jameson,, Craig Allen; Lic. No.: C30687 7225 CRESCENT PARK W #311      PLAYA VISTA, CA 90094
Contractor Shade Structures Inc; Lic. No.: 989458-B P O BOX 3467      COPELL, TX 75019
Engineer Bowen,, William Noble; Lic. No.: C32642 1937 BEDFORD RD      BEDFORD, TX 76021

Inspector Information

DERRICK SPENCER, (310) 914-3919 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/11/2024 Approved DERRICK SPENCER
Final 8/14/2024 Not Ready for Inspection DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 8/14/2024 SGSOV Approved DERRICK SPENCER
Smoke Detectors 8/14/2024 Approved DERRICK SPENCER
Verify Sprinkler Sign Off 8/14/2024 Approved DERRICK SPENCER
Wood Frame 8/14/2024 Approved DERRICK SPENCER
Final 9/20/2024 Conditional Approval GRANT WOODS
Final 1/2/2025 Not Ready for Inspection DERRICK SPENCER
Final 2/14/2025 Partial Approval DANIEL VARNUM