4347 S LYCEUM AVE 90066
Certificate Information: 4347 S LYCEUM AVE 90066
- Application / Permit
- 23010-10000-01874
- Plan Check / Job No.
- B23LA08248
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan***PROPOSED SINGLE FAMILY DWELING
- Permit Issued
- Issued on 9/20/2023
- Issuing Office
- Current Status
- CofO Issued on 4/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | SINA KHOSRAVI |
| Corrections Issued | 5/9/2023 | SINA KHOSRAVI |
| Quality Review Completed | 5/15/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 8/9/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 9/6/2023 | SINA KHOSRAVI |
| Plan Check Approved | 9/20/2023 | SINA KHOSRAVI |
| Issued | 9/20/2023 | APPLICANT |
| CofO in Progress | 4/29/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 4/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/29/2024 | DANIEL ORRANTE |
| CofO Issued | 4/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2023 | JASON NG |
| Sewer availability | Cleared | 6/12/2023 | JASON NG |
| Hydrant and Access approval | Cleared | 7/7/2023 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 7/14/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/17/2023 | JOSEPH RHYU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/6/2023 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 10/13/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/13/2023 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 10/23/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 11/16/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/16/2023 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 11/22/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 11/22/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 11/27/2023 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/5/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 12/5/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 12/5/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 12/5/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 12/6/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 12/8/2023 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 12/12/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 12/14/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 12/14/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/2/2024 | Approved | JESUS RODRIGUEZ |
| Final | 4/2/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 4/2/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 4/2/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 4/2/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Not Required | JESUS RODRIGUEZ |
| Service/Power Release | 4/2/2024 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 4/2/2024 | Approved | JESUS RODRIGUEZ |
| Final | 4/17/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 4/29/2024 | OK to Issue CofO | JESUS RODRIGUEZ |