2324 S VINEYARD AVE 90016

Certificate Information: 2324 S VINEYARD AVE 90016

Application / Permit
23010-10000-01859
Plan Check / Job No.
B23LA08176
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER MULTIPLE ADUs STATE LAW (1-STORY)
Permit Issued
Issued on 12/13/2023
Issuing Office
Current Status
CofO Issued on 7/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 CARLOS MONTES
Corrections Issued 5/24/2023 CARLOS MONTES
Quality Review Completed 5/24/2023 GARO TELMI
Applicant returned to address corrections 8/30/2023 CARLOS MONTES
Applicant returned to address corrections 9/19/2023 CARLOS MONTES
Plan Check Approved 12/11/2023 CARLOS MONTES
Issued 12/13/2023 APPLICANT
CofO in Progress 6/14/2024 JUSTIN HAWLEY
CofO in Progress 7/16/2024 JUSTIN HAWLEY
Permit Finaled 7/16/2024 DEROLD HAUFF
Permit Finaled 7/16/2024 DEROLD HAUFF
CofO Issued 7/16/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/1/2023 CELINA MORENO
Sewer availability Cleared 8/1/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/2/2023 CELINA MORENO
Address approval Cleared 8/15/2023 CELINA MORENO

Contact Information

Contractor Build Tuff Construction; Lic. No.: 1076283-B       ,
Engineer Sutrisno,, Raivyno; Lic. No.: C93874 19423 VANOWEN ST      RESEDA, CA 91335

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/2/2024 Not Ready for Inspection JUSTIN HAWLEY
Sewer 2/2/2024 Not Ready for Inspection JUSTIN HAWLEY
Underground Mechanical 2/2/2024 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 2/12/2024 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 2/23/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Partial Approval JUSTIN HAWLEY
Deputy Wood Construction 3/13/2024 Conditional Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 3/14/2024 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Rough 3/14/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 3/14/2024 Not Ready for Inspection JUSTIN HAWLEY
Green Building Rough 3/14/2024 Approved JUSTIN HAWLEY
HVAC-Rough 3/14/2024 Approved JUSTIN HAWLEY
PLUMBING-Rough 3/14/2024 Partial Approval JUSTIN HAWLEY
Sewer 3/14/2024 Partial Approval JUSTIN HAWLEY
Special/Order Compliance 3/14/2024 Corrections Issued JUSTIN HAWLEY
Wood Frame 3/15/2024 Partial Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 3/26/2024 Approved JUSTIN HAWLEY
Sewer 3/26/2024 Corrections Issued JUSTIN HAWLEY
Underground Mechanical 3/26/2024 Approved JUSTIN HAWLEY
Special/Order Compliance 3/29/2024 Not Ready for Inspection JUSTIN HAWLEY
Underground Mechanical 3/29/2024 Approved JUSTIN HAWLEY
Insulation 4/5/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 4/5/2024 Approved ROY SPAULDING
Drywall Nailing 4/9/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 4/9/2024 Approved JOSH MEISTER
Shower Pan 4/9/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 4/11/2024 Approved JUSTIN HAWLEY
Final 5/29/2024 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 5/29/2024 Approved RICHARD DOCKUS
ELECTRICAL-Final 6/6/2024 Approved JUSTIN HAWLEY
Final 6/6/2024 Not Ready for Inspection JUSTIN HAWLEY
Green Building Final 6/6/2024 Approved JUSTIN HAWLEY
HVAC-Final 6/6/2024 Approved JUSTIN HAWLEY
MERV13>=Final 6/6/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 6/6/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Not Required JUSTIN HAWLEY
Service/Power Release 6/6/2024 Not Ready for Inspection JUSTIN HAWLEY
Smoke Detectors 6/6/2024 Approved JUSTIN HAWLEY
Final 6/14/2024 OK to Issue CofO JUSTIN HAWLEY
Service/Power Release 6/14/2024 Approved JUSTIN HAWLEY
Final 7/16/2024 OK to Issue CofO JUSTIN HAWLEY