3935 1/2 W SENECA AVE 90039

Certificate Information: 3935 1/2 W SENECA AVE 90039

Application / Permit
23010-10000-01849
Plan Check / Job No.
B23LA08150
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Dettached Accessory Dwelling Unit at rear of the lot per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) **1 of 2**
Permit Issued
Issued on 5/3/2024
Issuing Office
Current Status
CofO Issued on 10/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2023 APPLICANT
Assigned to Plan Check Engineer 5/12/2023 EDWIN ESPIN
Corrections Issued 5/15/2023 EDWIN ESPIN
Applicant returned to address corrections 3/5/2024 ALFREDO JARA
Applicant returned to address corrections 4/18/2024 ALFREDO JARA
Plan Check Approved 4/26/2024 EDWIN ESPIN
Issued 5/3/2024 APPLICANT
CofO in Progress 10/22/2025 NICHOLAS LOPEZ
Permit Finaled 10/23/2025 DEROLD HAUFF
CofO Issued 10/23/2025 DEROLD HAUFF
Permit Finaled 10/23/2025 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 11/6/2023 RUBEN VASQUEZ
Low Impact Development (LID) Cleared 1/19/2024 SAMUEL LINN
Eng Process Fee Ord 176,300 Cleared 1/31/2024 JESSICA OPINION
Roof/Waste drainage to street Cleared 1/31/2024 JESSICA OPINION
Sewer availability Cleared 1/31/2024 JESSICA OPINION
Address approval Cleared 2/1/2024 JESSICA OPINION
Hold Cleared 5/31/2024 ALEXIS SCHULTZ

Contact Information

Contractor Advanced General Construction; Lic. No.: 951083-B       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/8/2024 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 8/12/2024 Partial Approval THOMAS LOGRASSO
Sewer 8/12/2024 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 8/19/2024 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 9/13/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 10/1/2024 Not Ready for Inspection THOMAS LOGRASSO
Underground Mechanical 11/1/2024 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 11/22/2024 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 1/17/2025 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 4/3/2025 Corrections Issued NICHOLAS LOPEZ
Interior/Exterior Lathing 4/3/2025 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Rough 4/3/2025 Corrections Issued NICHOLAS LOPEZ
BUILDING-Rough-Frame 4/8/2025 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Rough 4/8/2025 Approved NICHOLAS LOPEZ
Green Building Rough 4/8/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 4/8/2025 Corrections Issued NICHOLAS LOPEZ
Interior/Exterior Lathing 4/8/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 4/8/2025 Approved NICHOLAS LOPEZ
Verify Sprinkler Sign Off 4/8/2025 Not Ready for Inspection NICHOLAS LOPEZ
Insulation 4/16/2025 Corrections Issued NICHOLAS LOPEZ
Interior/Exterior Lathing 4/16/2025 Not Ready for Inspection NICHOLAS LOPEZ
BUILDING-Rough-Frame 4/18/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 4/18/2025 Approved NICHOLAS LOPEZ
Insulation 4/18/2025 Corrections Issued NICHOLAS LOPEZ
Verify Sprinkler Sign Off 4/18/2025 Approved NICHOLAS LOPEZ
Insulation 4/23/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 4/23/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 4/25/2025 Not Ready for Inspection NICHOLAS LOPEZ
Drywall Nailing 4/29/2025 Approved NICHOLAS LOPEZ
Shower Pan 4/29/2025 Corrections Issued NICHOLAS LOPEZ
Shower Pan 5/2/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 7/14/2025 Not Ready for Inspection NICHOLAS LOPEZ
Final 7/14/2025 Not Ready for Inspection NICHOLAS LOPEZ
Green Building Final 7/14/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 7/14/2025 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Final 7/14/2025 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 7/14/2025 SGSOV Not Ready NICHOLAS LOPEZ
Service/Power Release 7/14/2025 Not Ready for Inspection NICHOLAS LOPEZ
Smoke Detectors 7/14/2025 Not Ready for Inspection NICHOLAS LOPEZ
ELECTRICAL-Final 7/25/2025 Not Ready for Inspection NICHOLAS LOPEZ
Final 7/25/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 7/25/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 7/25/2025 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Final 7/25/2025 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Not Ready NICHOLAS LOPEZ
Service/Power Release 7/25/2025 Not Ready for Inspection NICHOLAS LOPEZ
Smoke Detectors 7/25/2025 Not Ready for Inspection NICHOLAS LOPEZ
ELECTRICAL-Final 7/31/2025 Corrections Issued NICHOLAS LOPEZ
Final 7/31/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 7/31/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 7/31/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 7/31/2025 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 7/31/2025 SGSOV No Gas NICHOLAS LOPEZ
Service/Power Release 7/31/2025 Not Ready for Inspection NICHOLAS LOPEZ
Smoke Detectors 7/31/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 8/19/2025 Corrections Issued NICHOLAS LOPEZ
Final 8/19/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 8/19/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 8/19/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 8/19/2025 Approved NICHOLAS LOPEZ
Service/Power Release 8/19/2025 Not Ready for Inspection NICHOLAS LOPEZ
Pre-Inspection 10/14/2025 Not Ready for Inspection NICHOLAS LOPEZ
Service/Power Release 10/14/2025 Not Ready for Inspection NICHOLAS LOPEZ
Final 10/17/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 10/17/2025 Approved NICHOLAS LOPEZ
Service/Power Release 10/17/2025 Not Required NICHOLAS LOPEZ
ELECTRICAL-Final 10/21/2025 Approved NICHOLAS LOPEZ
Final 10/21/2025 OK to Issue CofO NICHOLAS LOPEZ
Service/Power Release 10/21/2025 Not Required NICHOLAS LOPEZ