802 N EAST EDGEWARE ROAD 90026

Certificate Information: 802 N EAST EDGEWARE ROAD 90026

Application / Permit
23010-10000-01841
Plan Check / Job No.
B23LA08105
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3 STORY SINGLE FAMILY DWELLING W/ COURTYARD AND ROOF DECK
Permit Issued
Issued on 5/28/2024
Issuing Office
Valley
Current Status
Issued on 5/28/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/2/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 KHEDER ALRAZAA
Corrections Issued 5/24/2023 KHEDER ALRAZAA
Quality Review Completed 6/2/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 6/7/2023 APPLICANT
Applicant returned to address corrections 11/13/2023 ARSALAN SHABESTARI
Applicant returned to address corrections 4/1/2024 ARSALAN SHABESTARI
Applicant returned to address corrections 4/5/2024 KHEDER ALRAZAA
Applicant returned to address corrections 4/19/2024 KHEDER ALRAZAA
Applicant returned to address corrections 5/1/2024 KHEDER ALRAZAA
Plan Check Approved 5/9/2024 KHEDER ALRAZAA
Issued 5/28/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/7/2023 WALLIE JONG
BHO/Hillside ordinance Cleared 6/7/2023 WALLIE JONG
BHO/Hillside ordinance Cleared 6/7/2023 WALLIE JONG
BHO/Hillside ordinance Cleared 6/7/2023 WALLIE JONG
BHO/Hillside ordinance Cleared 6/7/2023 WALLIE JONG
Permit Cleared 6/7/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/3/2023 PAMELA TENEZA
Sewer availability Cleared 8/3/2023 PAMELA TENEZA
Address approval Cleared 12/7/2023 AMBER CAMPBELL
CPC Cleared 12/12/2023 RYAN LY
Miscellaneous Cleared 12/12/2023 NATHAN ROMINE
Tract Map conditions Cleared 12/12/2023 RYAN LY
Low Impact Development (LID) Cleared 3/25/2024 SAMUEL LINN
HPOZ Cleared 4/2/2024 SUKI GERSHENHORN
Miscellaneous Cleared 4/2/2024 SUKI GERSHENHORN
Roof/Waste drainage to street Cleared 4/9/2024 STEVE MELGAR
Hydrant and Access approval Cleared 4/15/2024 MATTHEW CRAIG
GPI Written Notices Cleared 4/19/2024 KHEDER ALRAZAA
Grading Pre-Inspection Cleared 4/19/2024 KHEDER ALRAZAA
Trees in Parkway Cleared 4/24/2024 ADALBERTO VERA

Contact Information

Architect Rotondi,, Michael; Lic. No.: C10351 600 MOULTON AVE #405      LOS ANGELES, CA 90031
Contractor Rolenconstruction Llc; Lic. No.: 1105889-B 5250 LANKERSHIM BLVD 500      NORTH HOLLYWOOD, CA 91601
Engineer Aoanan,, Virgilio Cendana; Lic. No.: C36079 1041 S GARFIELD AVE STE #210      ALHAMBRA, CA 91801
Engineer Daugherty,, Daniel Thomas; Lic. No.: C76588 31129 VIA COLINAS STE 707      WESTLAKE VILLAGE, CA 91362
Engineer Lewis,, Richard; Lic. No.: C90522 6044 HALM AVE      LOS ANGELES, CA 90056
Geologist Daugherty,, Daniel Thomas; Lic. No.: EG2569 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Geologist Kaligi,, Adam Azad; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387
Landscape Architect Mason,, Gary; Lic. No.: LA5938 12320 ROCHEDALE LANE      LOS ANGELES, CA 90049

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/10/2024 Partial Inspection HAMIK HARTOUNIAN
Piling/Pier/Caisson 7/12/2024 Partial Approval HAMIK HARTOUNIAN
Piling/Pier/Caisson 7/16/2024 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 8/2/2024 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/28/2024 Corrections Issued HAMIK HARTOUNIAN
Grounding or Bonding 8/28/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/30/2024 Corrections Issued HAMIK HARTOUNIAN
Grounding or Bonding 8/30/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 9/3/2024 Partial Approval HAMIK HARTOUNIAN
METHANE-Subgrade 10/10/2024 Approved FREDDIE RIVERA
Deputy Methane Barrier 10/17/2024 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/24/2024 Partial Approval HAMIK HARTOUNIAN
Deputy Methane Barrier 11/12/2024 Partial Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 11/14/2024 Partial Approval LUIS CASTRO
METHANE-Barrier 11/14/2024 Approved LUIS CASTRO
METHANE-Rough 11/14/2024 Partial Approval LUIS CASTRO
Masonry Wall/Backfill 12/6/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Reinforced Masonry Frame 12/6/2024 Corrections Issued HAMIK HARTOUNIAN
Masonry Wall/Backfill 12/9/2024 Not Ready for Inspection LUIS CASTRO
Reinforced Masonry Frame 12/9/2024 Not Ready for Inspection LUIS CASTRO
Masonry Wall/Backfill 12/10/2024 Partial Approval HAMIK HARTOUNIAN
Reinforced Masonry Frame 12/10/2024 Partial Approval HAMIK HARTOUNIAN
Masonry Wall/Backfill 1/6/2025 Partial Approval HAMIK HARTOUNIAN
Reinforced Masonry Frame 1/6/2025 Partial Approval HAMIK HARTOUNIAN
Deputy Methane Barrier 1/17/2025 Conditional Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/5/2025 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/7/2025 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 8/7/2025 Approved HAMIK HARTOUNIAN
Underground Mechanical 8/11/2025 Partial Approval HAMIK HARTOUNIAN
Sewer 10/1/2025 Approved HAMIK HARTOUNIAN
Underground Mechanical 10/1/2025 Approved HAMIK HARTOUNIAN
Wood Frame 11/25/2025 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/8/2025 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/26/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 2/26/2026 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 2/26/2026 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 2/26/2026 Not Ready for Inspection HAMIK HARTOUNIAN
METHANE-Rough 2/26/2026 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 2/26/2026 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/6/2026 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/6/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 3/6/2026 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 3/6/2026 Conditional Approval HAMIK HARTOUNIAN
MERV13>=Rough 3/6/2026 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/27/2026 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/27/2026 Approved HAMIK HARTOUNIAN
Green Building Rough 3/27/2026 Approved HAMIK HARTOUNIAN
HVAC-Rough 3/27/2026 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/15/2026 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 4/15/2026 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/7/2026 Approved HAMIK HARTOUNIAN
Insulation 5/7/2026 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/18/2026 Approved HAMIK HARTOUNIAN
Drywall Nailing 6/24/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 6/24/2026 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 7/2/2026 Approved GEM DE OCAMPO