3108 1/4 W 27TH ST 90018

Certificate Information: 3108 1/4 W 27TH ST 90018

Application / Permit
23010-10000-01838
Plan Check / Job No.
B22LA24369
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2 of 2: NEW ADU ( IRREGULAR SHAPED 21'-2" X 42'-3 1/8") PER GCS 65852.2(e)(1)(D) AND LAMC12.22 A.33(c)(d) AND (g)
Permit Issued
Issued on 2/9/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 NGHI SU
Corrections Issued 1/6/2023 NGHI SU
Quality Review Completed 1/18/2023 KEN GILL
Building Plans Picked Up 1/24/2023 APPLICANT
Applicant returned to address corrections 3/21/2023 NGHI SU
Plan Check Approved 9/1/2023 NGHI SU
Issued 2/9/2024 APPLICANT
CofO in Progress 5/22/2026 JUSTIN HAWLEY
CofO Issued 5/28/2026 DEROLD HAUFF
Permit Finaled 5/28/2026 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 6/6/2023 DANIEL MATA
ZI Cleared 6/6/2023 DANIEL MATA
Address approval Cleared 6/8/2023 JEANIE LAM
Sewer availability Cleared 6/8/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/13/2023 JEANIE LAM
Tenant Habitability Plan Cleared 6/15/2023 RICARDO BOHORQUEZ
Low Impact Development (LID) Cleared 8/24/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 8/28/2023 JESSICA OPINION

Contact Information

Contractor Mateos Construction & Remodeling Co; Lic. No.: 1034279-B 10378 MARKLEIN AVE      MISSION HILLS, CA 91345
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/4/2024 Partial Approval JUSTIN HAWLEY
Footing/Foundation/Slab 3/8/2024 Corrections Issued STUART CHAPMAN
Reinforced Concrete Frame 3/8/2024 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 3/8/2024 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 7/23/2024 Not Ready for Inspection JUSTIN HAWLEY
METHANE-Barrier 7/23/2024 Not Ready for Inspection JUSTIN HAWLEY
METHANE-Subgrade 7/23/2024 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 7/24/2024 Approved JUSTIN HAWLEY
METHANE-Barrier 7/24/2024 Approved JUSTIN HAWLEY
METHANE-Subgrade 7/24/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 8/16/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Partial Approval JUSTIN HAWLEY
Green Building Rough 8/16/2024 Not Ready for Inspection JUSTIN HAWLEY
HVAC-Rough 8/16/2024 Corrections Issued JUSTIN HAWLEY
METHANE-Rough 8/16/2024 Approved JUSTIN HAWLEY
PLUMBING-Rough 8/16/2024 Approved JUSTIN HAWLEY
Special/Order Compliance 8/16/2024 Corrections Issued JUSTIN HAWLEY
Insulation 8/23/2024 Corrections Issued JUSTIN HAWLEY
Interior/Exterior Lathing 8/23/2024 Approved JUSTIN HAWLEY
Special/Order Compliance 8/23/2024 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 8/27/2024 Approved JUSTIN HAWLEY
Insulation 8/27/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 8/27/2024 Approved JUSTIN HAWLEY
Drywall Nailing 9/4/2024 Approved JUSTIN HAWLEY
Green Building Rough 9/4/2024 Approved JUSTIN HAWLEY
Final 11/6/2025 Corrections Issued ENRIQUE MIRELES
Green Building Final 11/6/2025 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/6/2025 SGSOV Not Ready ENRIQUE MIRELES
Service/Power Release 11/6/2025 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 11/6/2025 Not Ready for Inspection ENRIQUE MIRELES
Final 11/18/2025 Not Ready for Inspection JUSTIN HAWLEY
Green Building Final 11/18/2025 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 11/18/2025 SGSOV Not Ready JUSTIN HAWLEY
Service/Power Release 11/18/2025 Not Ready for Inspection JUSTIN HAWLEY
Smoke Detectors 11/18/2025 Not Ready for Inspection JUSTIN HAWLEY
Service/Power Release 11/26/2025 Corrections Issued JUSTIN HAWLEY
Final 4/30/2026 Corrections Issued JUSTIN HAWLEY
Final 5/5/2026 Corrections Issued JUSTIN HAWLEY
Final 5/22/2026 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 5/22/2026 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Approved JUSTIN HAWLEY
Service/Power Release 5/22/2026 Approved JUSTIN HAWLEY
Smoke Detectors 5/22/2026 Approved JUSTIN HAWLEY