17104 W STAGG ST 91406

Certificate Information: 17104 W STAGG ST 91406

Application / Permit
23010-10000-01752
Plan Check / Job No.
B23LA07545
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
One story addition to (E) detached garage to expand garage by 50 SF and add 1200 SF ADU and 110 SF trellis, creating a detached ADU per Ordinance (1200 SF) with attached garage (413 SF) and attached trellis (110 SF). Work per licensed engineer.
Permit Issued
Issued on 11/7/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 CAROLEAN BASMA
Corrections Issued 5/5/2023 CAROLEAN BASMA
Building Plans Picked Up 5/17/2023 APPLICANT
Plan Check Approved 10/25/2023 DANIEL SMILEY
Issued 11/7/2023 APPLICANT
CofO in Progress 7/17/2024 RAUL OLAGI
Permit Finaled 8/7/2024 RUBEN SALAS
CofO Issued 8/7/2024 RUBEN SALAS
Permit Finaled 8/7/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/7/2023 MEGAN GODINEZ
Sewer availability Cleared 6/12/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/24/2023 MEGAN GODINEZ
Construction near power lines Cleared 9/22/2023 TINA MIRANDA
Low Impact Development (LID) Cleared 10/23/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 10/24/2023 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 PO BOX 5044      PASADENA, CA 91117

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/28/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 12/28/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 1/4/2024 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 1/8/2024 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 1/9/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval RAUL OLAGI
Deputy Wood Construction 3/13/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Not Ready for Inspection RAUL OLAGI
Rough-Elec/Plmb/HVAC 3/19/2024 Not Ready for Inspection RAUL OLAGI
Sewer 3/19/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 3/21/2024 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 3/21/2024 Approved RAUL OLAGI
Insulation 4/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 4/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Shower Pan 4/2/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 4/3/2024 Conditional Approval SALVADOR MARTINEZ
Interior/Exterior Lathing 4/5/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 4/9/2024 Approved RAUL OLAGI
Sewer 5/17/2024 Partial Inspection SALVADOR MARTINEZ
Underground Mechanical 5/17/2024 Corrections Issued SALVADOR MARTINEZ
Gas Test 5/20/2024 Approved SALVADOR MARTINEZ
Underground Mechanical 5/20/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/28/2024 Approved RAUL OLAGI
ELECTRICAL-Final 6/28/2024 Approved RAUL OLAGI
Final 6/28/2024 Corrections Issued RAUL OLAGI
Green Building Final 6/28/2024 Approved RAUL OLAGI
Green Building Rough 6/28/2024 Approved RAUL OLAGI
HVAC-Final 6/28/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 6/28/2024 Approved RAUL OLAGI
Final 7/17/2024 OK to Issue CofO RAUL OLAGI
Service/Power Release 7/17/2024 Approved RAUL OLAGI