3474 S ROSEWOOD AVE 90066

Certificate Information: 3474 S ROSEWOOD AVE 90066

Application / Permit
23010-10000-01721
Plan Check / Job No.
B23LA07394
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1- STORY ADU PER STATE LAW
Permit Issued
Issued on 7/19/2023
Issuing Office
Metro
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 JAD BASMA
Corrections Issued 5/19/2023 JAD BASMA
Quality Review Completed 5/23/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 5/25/2023 APPLICANT
Applicant returned to address corrections 7/11/2023 JAD BASMA
Plan Check Approved 7/19/2023 JAD BASMA
Issued 7/19/2023 APPLICANT
CofO in Progress 10/8/2024 JESUS RODRIGUEZ
CofO Issued 10/22/2024 RICHARD STEINBACH
Permit Finaled 10/22/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/2/2023 ALEXANDER HELFER
Address approval Cleared 6/9/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/12/2023 JEANIE LAM
Sewer availability Cleared 6/12/2023 JEANIE LAM
Specific Plan Cleared 6/12/2023 FREDDY GARCIA
Low Impact Development (LID) Cleared 6/29/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 6/30/2023 JEANIE LAM
GPI Written Notices Cleared 7/19/2023 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/31/2023 Corrections Issued JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/31/2023 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 7/31/2023 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 8/1/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 8/1/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 8/11/2023 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 10/31/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 10/31/2023 Approved JESUS RODRIGUEZ
Underground Mechanical 10/31/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 11/2/2023 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 11/8/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/28/2023 Approved JESUS RODRIGUEZ
Green Building Rough 11/28/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/28/2023 Approved JESUS RODRIGUEZ
Shower Pan 11/28/2023 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 11/28/2023 Approved JESUS RODRIGUEZ
Insulation 12/11/2023 Approved JESUS PINEDA
Drywall Nailing 12/15/2023 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 1/12/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 5/1/2024 Approved JESUS RODRIGUEZ
Gas Test 5/14/2024 Approved JESUS RODRIGUEZ
HVAC-Final 5/14/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 5/14/2024 Approved JESUS RODRIGUEZ
Final 5/16/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 5/16/2024 Approved JESUS RODRIGUEZ
Green Building Final 5/16/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 5/16/2024 Approved JESUS RODRIGUEZ
Smoke Detectors 5/16/2024 Approved JESUS RODRIGUEZ
Final 5/21/2024 Not Ready for Inspection JESUS RODRIGUEZ
Final 10/7/2024 OK to Issue CofO JESUS RODRIGUEZ