10508 W WILKINS AVE 90024

Certificate Information: 10508 W WILKINS AVE 90024

Application / Permit
23010-10000-01717
Plan Check / Job No.
B23LA07378
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 12/27/2023
Issuing Office
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 CARLOS MONTES
Corrections Issued 5/1/2023 CARLOS MONTES
Quality Review Completed 5/5/2023 KEN GILL
Building Plans Picked Up 5/17/2023 APPLICANT
Applicant returned to address corrections 7/10/2023 CARLOS MONTES
Applicant returned to address corrections 12/1/2023 CARLOS MONTES
Plan Check Approved 12/1/2023 CARLOS MONTES
No Progress 12/1/2023 CARLOS MONTES
Plan Check Approved 12/21/2023 CARLOS MONTES
Issued 12/27/2023 APPLICANT
Permit Finaled 10/14/2025 RICHARD STEINBACH
CofO Issued 10/14/2025 RICHARD STEINBACH
Permit Finaled 10/14/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/22/2023 DARIN LAM
Sewer availability Cleared 5/22/2023 DARIN LAM
Hydrant and Access approval Cleared 6/9/2023 RUEL COLE
GPI Written Notices Cleared 7/10/2023 CARLOS MONTES
Grading Pre-Inspection Cleared 7/10/2023 CARLOS MONTES
Permit Cleared 7/17/2023 DARIN LAM
Specific Plan Cleared 7/31/2023 PEDRO AYALA
Trees in Parkway Cleared 8/15/2023 ADALBERTO VERA
Low Impact Development (LID) Cleared 11/9/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/15/2023 DARIN LAM

Contact Information

Contractor Drexel Construction Management Llc; Lic. No.: 1014160-B 5168 W PICO BLVD      LOS ANGELES, CA 90019
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 5/7/2024 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Subgrade 5/7/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 5/7/2024 Corrections Issued ASHLEY THOMPSON
Underground Mechanical 5/7/2024 Corrections Issued ASHLEY THOMPSON
METHANE-Subgrade 5/8/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 5/8/2024 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 6/5/2024 Approved KIRK SANDERS
METHANE-Barrier 6/5/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 8/26/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 9/6/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/12/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/16/2024 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 9/18/2024 Partial Approval KIRK SANDERS
Final 9/18/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 10/10/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 10/15/2024 Approved KIRK SANDERS
HVAC-Final 10/15/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 10/15/2024 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 10/15/2024 Partial Approval KIRK SANDERS
Special/Order Compliance 10/15/2024 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 10/23/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 10/25/2024 Conditional Approval KIRK SANDERS
Green Building Rough 10/25/2024 Approved KIRK SANDERS
HVAC-Final 10/25/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 10/25/2024 Conditional Approval KIRK SANDERS
METHANE-Rough 10/25/2024 Corrections Issued KIRK SANDERS
Verify Sprinkler Sign Off 10/25/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 11/1/2024 Approved KIRK SANDERS
Insulation 11/1/2024 Approved KIRK SANDERS
METHANE-Rough 11/1/2024 Approved KIRK SANDERS
Drywall Nailing 11/6/2024 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 11/15/2024 Partial Approval KIRK SANDERS
Shower Pan 11/15/2024 Approved KIRK SANDERS
Drywall Nailing 11/21/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 11/21/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 6/24/2025 Corrections Issued KIRK SANDERS
HVAC-Final 6/24/2025 Approved KIRK SANDERS
ELECTRICAL-Final 6/26/2025 Approved KIRK SANDERS
PLUMBING-Final 6/26/2025 Corrections Issued KIRK SANDERS
Service/Power Release 6/26/2025 Not Ready for Inspection KIRK SANDERS
Special/Order Compliance 6/26/2025 Corrections Issued KIRK SANDERS
Final 9/15/2025 Corrections Issued ARAM AVEDISIAN
Green Building Final 9/15/2025 Approved ARAM AVEDISIAN
PLUMBING-Final 9/15/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Not Required ARAM AVEDISIAN
Service/Power Release 9/15/2025 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 9/15/2025 Approved ARAM AVEDISIAN
Final 10/6/2025 Corrections Issued MICHAEL ALLEN
Final 10/8/2025 Conditional Approval MICHAEL ALLEN
Service/Power Release 10/8/2025 Approved MICHAEL ALLEN