5017 1/2 S CIMARRON ST 90062

Certificate Information: 5017 1/2 S CIMARRON ST 90062

Application / Permit
23010-10000-01713
Plan Check / Job No.
B23LA07355
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 21' X 32' DETACHED ACCESSORY UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g).
Permit Issued
Issued on 8/16/2023
Issuing Office
Current Status
CofO Issued on 3/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 4/25/2023 OMAR GARNICA
Corrections Issued 4/26/2023 OMAR GARNICA
Applicant returned to address corrections 5/30/2023 OMAR GARNICA
Plan Check Approved 8/16/2023 OMAR GARNICA
Issued 8/16/2023 APPLICANT
CofO in Progress 3/25/2025 SABAS ALONSO
Permit Finaled 3/26/2025 DEROLD HAUFF
CofO Issued 3/26/2025 DEROLD HAUFF
Permit Finaled 3/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/1/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/2/2023 TREVOR QUAN
Sewer availability Cleared 5/2/2023 TREVOR QUAN
Low Impact Development (LID) Cleared 6/23/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/26/2023 STEVE MELGAR
Construction near power lines Cleared 8/11/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/5/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 10/5/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Partial Approval SABAS ALONSO
Sewer 10/27/2023 Approved SABAS ALONSO
Underground Mechanical 10/27/2023 Partial Approval SABAS ALONSO
Insulation 10/31/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Approved SABAS ALONSO
PLUMBING-Rough 11/27/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 12/6/2023 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 12/14/2023 Approved SABAS ALONSO
PLUMBING-Rough 12/14/2023 Approved SABAS ALONSO
Underground Mechanical 12/14/2023 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 1/10/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 1/10/2024 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 2/21/2024 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 2/21/2024 Approved SABAS ALONSO
Green Building Rough 3/13/2024 No Access for Inspection SABAS ALONSO
BUILDING-Rough-Frame 3/15/2024 Partial Approval CRAIG DAVIS
Green Building Final 3/15/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 3/15/2024 Approved CRAIG DAVIS
Insulation 3/19/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 4/1/2024 Approved SABAS ALONSO
Insulation 4/1/2024 Approved SABAS ALONSO
Drywall Nailing 4/8/2024 Approved JOSH MEISTER
BUILDING-Rough-Frame 6/25/2024 Approved SABAS ALONSO
Final 6/25/2024 Corrections Issued SABAS ALONSO
Green Building Final 6/25/2024 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/25/2024 SGSOV Not Ready SABAS ALONSO
Service/Power Release 6/25/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 6/25/2024 Corrections Issued SABAS ALONSO
Verify Sprinkler Sign Off 6/25/2024 Not Ready for Inspection SABAS ALONSO
Final 9/5/2024 Corrections Issued SABAS ALONSO
Green Building Final 9/5/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/5/2024 SGSOV Not Ready SABAS ALONSO
Service/Power Release 9/5/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 9/5/2024 Approved SABAS ALONSO
Final 2/6/2025 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Not Ready SABAS ALONSO
Service/Power Release 2/6/2025 Not Ready for Inspection SABAS ALONSO
Final 2/14/2025 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/14/2025 SGSOV Approved SABAS ALONSO
Final 3/5/2025 Corrections Issued JOSE MACIAS
Service/Power Release 3/5/2025 Conditional Approval JOSE MACIAS
Service/Power Release 3/13/2025 Not Ready for Inspection SABAS ALONSO
Final 3/24/2025 OK to Issue CofO SABAS ALONSO