5017 1/2 S CIMARRON ST 90062
Certificate Information: 5017 1/2 S CIMARRON ST 90062
- Application / Permit
- 23010-10000-01713
- Plan Check / Job No.
- B23LA07355
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 21' X 32' DETACHED ACCESSORY UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g).
- Permit Issued
- Issued on 8/16/2023
- Issuing Office
- Current Status
- CofO Issued on 3/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2023 | OMAR GARNICA |
| Corrections Issued | 4/26/2023 | OMAR GARNICA |
| Applicant returned to address corrections | 5/30/2023 | OMAR GARNICA |
| Plan Check Approved | 8/16/2023 | OMAR GARNICA |
| Issued | 8/16/2023 | APPLICANT |
| CofO in Progress | 3/25/2025 | SABAS ALONSO |
| Permit Finaled | 3/26/2025 | DEROLD HAUFF |
| CofO Issued | 3/26/2025 | DEROLD HAUFF |
| Permit Finaled | 3/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 5/2/2023 | TREVOR QUAN |
| Low Impact Development (LID) | Cleared | 6/23/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/26/2023 | STEVE MELGAR |
| Construction near power lines | Cleared | 8/11/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/5/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 10/5/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Partial Approval | SABAS ALONSO |
| Sewer | 10/27/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 10/27/2023 | Partial Approval | SABAS ALONSO |
| Insulation | 10/31/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 11/27/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/6/2023 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Rough | 12/14/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/14/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 12/14/2023 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 1/10/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/10/2024 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 2/21/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 2/21/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 3/13/2024 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/15/2024 | Partial Approval | CRAIG DAVIS |
| Green Building Final | 3/15/2024 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Rough | 3/15/2024 | Approved | CRAIG DAVIS |
| Insulation | 3/19/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 4/1/2024 | Approved | SABAS ALONSO |
| Insulation | 4/1/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/8/2024 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 6/25/2024 | Approved | SABAS ALONSO |
| Final | 6/25/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 6/25/2024 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/25/2024 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 6/25/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 6/25/2024 | Corrections Issued | SABAS ALONSO |
| Verify Sprinkler Sign Off | 6/25/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 9/5/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 9/5/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/5/2024 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 9/5/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 9/5/2024 | Approved | SABAS ALONSO |
| Final | 2/6/2025 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 2/6/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 2/14/2025 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Approved | SABAS ALONSO |
| Final | 3/5/2025 | Corrections Issued | JOSE MACIAS |
| Service/Power Release | 3/5/2025 | Conditional Approval | JOSE MACIAS |
| Service/Power Release | 3/13/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 3/24/2025 | OK to Issue CofO | SABAS ALONSO |