1012 N WILCOX AVE 90038
Certificate Information: 1012 N WILCOX AVE 90038
- Application / Permit
- 23010-10000-01702
- Plan Check / Job No.
- B23LA07292
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan *New detached ADU with attached 2 car garage and storage at rear of site per LAMC 12.22 A.33 (c) and (d)
- Permit Issued
- Issued on 6/17/2024
- Issuing Office
- Current Status
- CofO Issued on 8/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 5/17/2023 | MARCELA FRANQUEZ |
| Quality Review Completed | 5/23/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 10/18/2023 | MARCELA FRANQUEZ |
| Plan Check Approved | 2/21/2024 | MARCELA FRANQUEZ |
| Issued | 6/17/2024 | APPLICANT |
| CofO in Progress | 8/8/2025 | JEFFREY MEAD |
| Permit Finaled | 8/11/2025 | DEROLD HAUFF |
| CofO Issued | 8/11/2025 | DEROLD HAUFF |
| Permit Finaled | 8/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2023 | JESSICA OPINION |
| Low Impact Development (LID) | Cleared | 8/15/2023 | SAMUEL LINN |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 8/17/2023 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 8/20/2023 | AHMED AMARRAGY |
Contact Information
| Architect | Phakos,, Cynthia; Lic. No.: C23352 | 9010 RANGELY AVE WEST HOLLYWOOD, CA 90048 |
| Contractor | Champion Builders Inc; Lic. No.: 1072812-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/6/2024 | Partial Approval | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 8/12/2024 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/13/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/29/2024 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 8/29/2024 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 8/29/2024 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 8/29/2024 | Partial Approval | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 8/29/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/10/2024 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/23/2024 | Approved | JEFFREY MEAD |
| Sewer | 10/18/2024 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 11/26/2024 | Conditional Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 12/6/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Sewer | 12/6/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 1/16/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/22/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 1/22/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 1/22/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 1/22/2025 | Approved | JEFFREY MEAD |
| Shower Pan | 1/22/2025 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 1/22/2025 | Approved | JEFFREY MEAD |
| Insulation | 1/29/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 2/6/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 2/6/2025 | Partial Approval | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 3/28/2025 | Partial Approval | WILLIAM SIERRA |
| Interior/Exterior Lathing | 4/1/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 6/10/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 6/10/2025 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Final | 6/24/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 6/24/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 6/24/2025 | Approved | RONNIE MINDANAO |
| HVAC-Final | 6/24/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 6/24/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 6/24/2025 | SGSOV Not Required | RONNIE MINDANAO |
| Service/Power Release | 6/24/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 6/24/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 6/27/2025 | Approved | JOSE MACIAS |
| Final | 6/27/2025 | Corrections Issued | JOSE MACIAS |
| Service/Power Release | 6/27/2025 | Not Ready for Inspection | JOSE MACIAS |
| Final | 8/7/2025 | OK to Issue CofO | JEFFREY MEAD |
| Service/Power Release | 8/7/2025 | Approved | JEFFREY MEAD |