23393 W SCHOOLCRAFT ST 91307
Certificate Information: 23393 W SCHOOLCRAFT ST 91307
- Application / Permit
- 23010-10000-01697
- Plan Check / Job No.
- B23LA07261
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW DETACHED 1 STORY ADU IN REAR DETACHED ADU PER LAMC 12.22 A.33 (c) & (d)
- Permit Issued
- Issued on 11/17/2023
- Issuing Office
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | ADRIANA LOPEZ |
| Corrections Issued | 6/7/2023 | ADRIANA LOPEZ |
| Building Plans Picked Up | 6/16/2023 | APPLICANT |
| Quality Review Completed | 6/26/2023 | KEN GILL |
| Applicant returned to address corrections | 9/19/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 9/27/2023 | ADRIANA LOPEZ |
| Issued | 11/17/2023 | APPLICANT |
| CofO in Progress | 9/5/2024 | TROY SANDERS |
| No Progress | 1/2/2025 | HENRY KIM |
| CofO in Progress | 1/2/2025 | HENRY KIM |
| Permit Finaled | 1/9/2025 | JOHN JANSON |
| CofO Issued | 1/9/2025 | JOHN JANSON |
| Permit Finaled | 1/9/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2023 | ROMAN GUTIERREZ |
| Watercourse | Cleared | 7/13/2023 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 8/3/2023 | TINA MIRANDA |
| Construction within easement | Cleared | 8/3/2023 | TINA MIRANDA |
| Low Impact Development (LID) | Cleared | 8/17/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/18/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/22/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/22/2023 | Not Ready for Inspection | TROY SANDERS |
| Pre-Inspection | 11/28/2023 | Corrections Issued | HORACE FULTZ |
| PLUMBING-Rough | 12/11/2023 | Partial Approval | TROY SANDERS |
| Sewer | 12/11/2023 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 12/19/2023 | Approved | TROY SANDERS |
| Deputy Reinf. Concrete | 12/27/2023 | Conditional Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2024 | Approved | TROY SANDERS |
| PLUMBING-Rough | 2/8/2024 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/15/2024 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 3/21/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| HVAC-Rough | 3/21/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 3/26/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 3/26/2024 | Partial Approval | GEVORK IPCHYAN |
| Insulation | 4/3/2024 | Approved | TROY SANDERS |
| Drywall Nailing | 6/3/2024 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 6/3/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 6/12/2024 | Partial Approval | TROY SANDERS |
| Service/Power Release | 6/12/2024 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/7/2024 | Approved | TROY SANDERS |
| Final | 8/7/2024 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 8/7/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/7/2024 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 8/7/2024 | Approved | TROY SANDERS |
| Service/Power Release | 8/15/2024 | Approved | TROY SANDERS |
| Final | 9/5/2024 | OK to Issue CofO | TROY SANDERS |