1141 1/4 W 45TH ST 90037
Certificate Information: 1141 1/4 W 45TH ST 90037
- Application / Permit
- 23010-10000-01668
- Plan Check / Job No.
- B23LA07151
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY DETACHED A.D.U. BEHIND FRONT UNIT OF (E) DUPLEX PER STATE LAW. CONST. PER W.F.P.P. "COMPLY WITH DEPARTMENT ORDER effective date 11/02/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 10/29/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 4/24/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 5/1/2023 | APPLICANT |
| Applicant returned to address corrections | 5/22/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 7/11/2024 | SUNMIN LEE |
| Plan Check Approved | 10/21/2024 | MINA HABILI |
| Issued | 10/29/2024 | APPLICANT |
| CofO in Progress | 12/30/2025 | BARRY HACHE |
| Permit Finaled | 1/5/2026 | DEROLD HAUFF |
| CofO Issued | 1/5/2026 | DEROLD HAUFF |
| Permit Finaled | 1/5/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 6/28/2023 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 6/28/2023 | CINDY QI |
| Address approval | Cleared | 7/3/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2023 | CINDY QI |
| Sewer availability | Cleared | 7/10/2023 | CINDY QI |
| Senate Bill 9 | Cleared | 8/22/2023 | JASON CHAN |
| Community Plan Implem. Overlay | Cleared | 8/23/2023 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 6/17/2024 | TINA MIRANDA |
| Community Plan Implem. Overlay | Cleared | 7/1/2024 | DYNL MIRANDA |
Contact Information
| Contractor | Ruiz Development & Enigneering; Lic. No.: 1120759-B | 10400 ROUSELLE DR JURUPA VALLEY, CA 91752 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/17/2024 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 12/23/2024 | Corrections Issued | BARRY HACHE |
| Sewer | 12/23/2024 | Approved | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 12/24/2024 | Not Ready for Inspection | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 12/30/2024 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 3/12/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Rough | 3/12/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 3/12/2025 | Approved | BARRY HACHE |
| PLUMBING-Rough | 3/12/2025 | Not Ready for Inspection | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 3/13/2025 | Approved | BARRY HACHE |
| Underground Mechanical | 3/13/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 3/14/2025 | Not Ready for Inspection | BARRY HACHE |
| Green Building Rough | 3/14/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 3/14/2025 | Approved | BARRY HACHE |
| Insulation | 3/21/2025 | Approved | JOSH MEISTER |
| Drywall Nailing | 4/18/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 4/18/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 4/22/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 5/5/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Rough | 5/9/2025 | Approved | BARRY HACHE |
| Pre-Inspection | 5/9/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 5/16/2025 | Approved | BARRY HACHE |
| Service/Power Release | 5/23/2025 | Conditional Approval | BARRY HACHE |
| ELECTRICAL-Final | 9/12/2025 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 9/12/2025 | Approved | BARRY HACHE |
| Green Building Final | 9/12/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 9/15/2025 | Approved | BARRY HACHE |
| Final | 9/15/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 9/15/2025 | Approved | BARRY HACHE |
| HVAC-Final | 9/15/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 9/15/2025 | Approved | BARRY HACHE |
| Smoke Detectors | 9/15/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 10/15/2025 | Corrections Issued | BRENDAN MORELLI |
| Final | 10/15/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 10/15/2025 | SGSOV No Gas | BRENDAN MORELLI |
| Service/Power Release | 10/15/2025 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 12/23/2025 | Approved | BARRY HACHE |
| Final | 12/23/2025 | Corrections Issued | BARRY HACHE |
| Final | 12/30/2025 | OK to Issue CofO | BARRY HACHE |