412 N AVENUE 61 90042
Certificate Information: 412 N AVENUE 61 90042
- Application / Permit
- 23010-10000-01666
- Plan Check / Job No.
- B23LA07145
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan****PROPOSED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 8/4/2024
- Issuing Office
- Current Status
- CofO Issued on 5/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | SINA KHOSRAVI |
| Corrections Issued | 5/18/2023 | SINA KHOSRAVI |
| Quality Review Completed | 5/23/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 6/22/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 6/13/2024 | SINA KHOSRAVI |
| Plan Check Approved | 8/1/2024 | SINA KHOSRAVI |
| Issued | 8/4/2024 | APPLICANT |
| CofO in Progress | 5/7/2025 | LILIANA PORTILLO |
| Permit Finaled | 5/10/2025 | DEROLD HAUFF |
| CofO Issued | 5/10/2025 | DEROLD HAUFF |
| Permit Finaled | 5/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 6/1/2023 | DAVID URITA |
| Address approval | Cleared | 8/1/2023 | JOSEPH RHYU |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | JOSEPH RHYU |
| HPOZ | Cleared | 9/5/2023 | MICAELA TORRES-GIL |
| Sewer availability | Cleared | 10/19/2023 | JOSEPH RHYU |
| Low Impact Development (LID) | Cleared | 2/1/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 2/21/2024 | CHRISTINA BRACO |
| Grading Pre-Inspection | Cleared | 5/23/2024 | LANNY MERRICK |
| GPI Written Notices | Cleared | 7/30/2024 | SINA KHOSRAVI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/16/2024 | Partial Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 8/21/2024 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/21/2024 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Partial Approval | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 8/29/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 9/18/2024 | Approved | JEFFREY MEAD |
| Wood Frame | 9/18/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Deputy Wood Construction | 9/19/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Not Ready for Inspection | ROY SPAULDING |
| Wood Frame | 9/23/2024 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 9/30/2024 | Approved | ROY SPAULDING |
| Gas Test | 9/30/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 9/30/2024 | Approved | ROY SPAULDING |
| Rough-Elec/Plmb/HVAC | 9/30/2024 | Approved | ROY SPAULDING |
| Sewer | 9/30/2024 | Approved | ROY SPAULDING |
| Insulation | 10/2/2024 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/2/2024 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 10/7/2024 | Approved | LILIANA PORTILLO |
| Insulation | 10/7/2024 | Approved | LILIANA PORTILLO |
| Shower Pan | 10/7/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/17/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 11/26/2024 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 11/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 11/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 11/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/26/2024 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 11/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 11/26/2024 | Approved | LILIANA PORTILLO |
| Final | 12/16/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 3/20/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 3/20/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/20/2025 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 3/20/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 5/6/2025 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 5/6/2025 | Approved | LILIANA PORTILLO |