10413 S ANZAC AVE 90002

Certificate Information: 10413 S ANZAC AVE 90002

Application / Permit
23010-10000-01634
Plan Check / Job No.
B23LA06969
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) TWO STORY RESIDENCE WITH ONE CAR GARAGE AND ONE CAR CARPORT.
Permit Issued
Issued on 12/27/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 TSE MING HUANG
Corrections Issued 4/24/2023 TSE MING HUANG
Quality Review Completed 4/28/2023 KEN GILL
Building Plans Picked Up 5/1/2023 APPLICANT
Plan Check Approved 12/20/2023 TSE MING HUANG
Issued 12/27/2023 APPLICANT
CofO in Progress 2/26/2025 BEN MOLSTAD
CofO Issued 3/3/2025 ANSON MAGLASANG
Permit Finaled 3/3/2025 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/25/2023 JOSEPH RHYU
Sewer availability Cleared 6/25/2023 JOSEPH RHYU
Hydrant and Access approval Cleared 7/7/2023 GILBERT URREA
Low Impact Development (LID) Cleared 12/13/2023 SAMUEL LINN
Address approval Cleared 12/14/2023 JOSEPH RHYU
Roof/Waste drainage to street Cleared 12/14/2023 JOSEPH RHYU

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B 9214 MANZANAR AVE      DOWNEY, CA 90240
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/24/2024 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 1/24/2024 Not Ready for Inspection JAMES CHAVEZ
Special/Order Compliance 1/24/2024 Corrections Issued JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 1/25/2024 Approved JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 2/12/2024 Not Ready for Inspection BEN MOLSTAD
Footing/Foundation/Slab 2/12/2024 Not Ready for Inspection BEN MOLSTAD
Footing/Foundation/Slab 2/27/2024 Approved BEN MOLSTAD
PLUMBING-Rough 2/27/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Approval BEN MOLSTAD
BUILDING-Rough-Frame 4/25/2024 Partial Approval BEN MOLSTAD
Sewer 4/25/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Partial Approval BEN MOLSTAD
BUILDING-Rough-Frame 6/4/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 6/4/2024 Corrections Issued BEN MOLSTAD
Green Building Rough 6/4/2024 Approved BEN MOLSTAD
HVAC-Rough 6/4/2024 Approved BEN MOLSTAD
PLUMBING-Rough 6/4/2024 Not Ready for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 6/4/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 6/17/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 6/17/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 6/17/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 6/17/2024 Approved BEN MOLSTAD
PLUMBING-Rough 6/17/2024 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 6/20/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 6/20/2024 Approved BEN MOLSTAD
PLUMBING-Rough 6/20/2024 Approved BEN MOLSTAD
Wood Frame 6/20/2024 Approved BEN MOLSTAD
Insulation 9/11/2024 Approved BARRY HACHE
BUILDING-Rough-Frame 9/18/2024 Approved BARRY HACHE
Drywall Nailing 9/18/2024 Approved BARRY HACHE
Final 1/30/2025 Corrections Issued ANTHONY EGSON
Green Building Final 1/30/2025 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/30/2025 SGSOV Approved ANTHONY EGSON
Service/Power Release 1/30/2025 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 1/30/2025 Approved ANTHONY EGSON
Final 2/6/2025 No Access for Inspection ANTHONY EGSON
Green Building Final 2/6/2025 No Access for Inspection ANTHONY EGSON
Service/Power Release 2/6/2025 No Access for Inspection ANTHONY EGSON
ELECTRICAL-Final 2/25/2025 Approved BEN MOLSTAD
Final 2/25/2025 OK to Issue CofO BEN MOLSTAD
Green Building Final 2/25/2025 Approved BEN MOLSTAD
HVAC-Final 2/25/2025 Approved BEN MOLSTAD
PLUMBING-Final 2/25/2025 Approved BEN MOLSTAD
Service/Power Release 2/25/2025 Approved BEN MOLSTAD