4354 S STEWART AVE 90066

Certificate Information: 4354 S STEWART AVE 90066

Application / Permit
23010-10000-01604
Plan Check / Job No.
B23LA06850
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan Convert existing garage with addition to new 1 story 1200 sf ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 8/23/2023
Issuing Office
Current Status
CofO Issued on 10/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2023 APPLICANT
Assigned to Plan Check Engineer 4/19/2023 ADAM HEGAZI
Corrections Issued 4/20/2023 ADAM HEGAZI
Applicant returned to address corrections 6/27/2023 ADAM HEGAZI
Plan Check Approved 8/16/2023 ADAM HEGAZI
Issued 8/23/2023 APPLICANT
CofO in Progress 10/10/2024 TEMISTOCLES CAAL
Permit Finaled 10/15/2024 RICHARD STEINBACH
CofO Issued 10/15/2024 RICHARD STEINBACH
Permit Finaled 10/15/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/21/2023 JASON NG
Roof/Waste drainage to street Cleared 4/21/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 4/27/2023 JASON NG
Sewer availability Cleared 4/27/2023 JASON NG
Specific Plan Cleared 5/4/2023 JOSHUA JONES
Low Impact Development (LID) Cleared 6/28/2023 SHAHIN KHAZEY
Construction near power lines Cleared 8/16/2023 TINA MIRANDA

Contact Information

Contractor Sklar Construction Inc; Lic. No.: 1034994-B       ,
Engineer Tabirara,, Vernon Nicolas; Lic. No.: C75492 17520 DAPHNE AVE      TORRANCE, CA 90504

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/18/2023 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 10/25/2023 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/25/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 10/25/2023 Approved JESUS RODRIGUEZ
Underground Mechanical 10/25/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 12/21/2023 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Approved TEMISTOCLES CAAL
Gas Test 1/4/2024 Partial Approval TEMISTOCLES CAAL
Green Building Rough 1/4/2024 Not Ready for Inspection TEMISTOCLES CAAL
HVAC-Rough 1/4/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 1/4/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 1/22/2024 Not Ready for Inspection TEMISTOCLES CAAL
Gas Test 1/22/2024 Approved TEMISTOCLES CAAL
HVAC-Rough 1/22/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 1/26/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 1/26/2024 Approved TEMISTOCLES CAAL
Green Building Rough 1/26/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 1/26/2024 Approved TEMISTOCLES CAAL
Underground Mechanical 1/26/2024 Approved TEMISTOCLES CAAL
Insulation 2/27/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 3/4/2024 Approved TEMISTOCLES CAAL
Gas Test 4/2/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 4/2/2024 Approved TEMISTOCLES CAAL
Shower Pan 4/2/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 6/26/2024 Approved TEMISTOCLES CAAL
Final 6/26/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 6/26/2024 Approved TEMISTOCLES CAAL
HVAC-Final 6/26/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 6/26/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 6/26/2024 SGSOV Approved TEMISTOCLES CAAL
Service/Power Release 6/26/2024 Approved TEMISTOCLES CAAL
Smoke Detectors 6/26/2024 Approved TEMISTOCLES CAAL
Final 10/9/2024 OK to Issue CofO TEMISTOCLES CAAL