1503 N MOHAWK ST 90026

Certificate Information: 1503 N MOHAWK ST 90026

Application / Permit
23010-10000-01572
Plan Check / Job No.
B23LA06719
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 1-story ADU PER STATE LAW (CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)), CONSTRUCTION PER ENGINEERED DESIGN.
Permit Issued
Issued on 5/8/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2023 APPLICANT
Assigned to Plan Check Engineer 4/14/2023 CAROLEAN BASMA
Corrections Issued 4/18/2023 CAROLEAN BASMA
Building Plans Picked Up 4/20/2023 APPLICANT
Applicant returned to address corrections 4/26/2023 MINA HABILI
Plan Check Approved 5/3/2023 DANIEL SMILEY
Issued 5/8/2023 APPLICANT
CofO in Progress 11/17/2023 THOMAS LOGRASSO
CofO Issued 12/4/2023 DEROLD HAUFF
Permit Finaled 12/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/27/2023 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 4/27/2023 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 4/27/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 4/28/2023 CHRISTOPHER ROCHA
Grading Pre-Inspection Cleared 5/2/2023 ALEXANDER HELFER

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/12/2023 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 5/12/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 6/8/2023 Partial Approval THOMAS LOGRASSO
Gas Test 6/8/2023 Partial Approval THOMAS LOGRASSO
Green Building Rough 6/8/2023 Not Ready for Inspection THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 6/8/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 6/13/2023 Approved THOMAS LOGRASSO
Insulation 6/13/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 6/13/2023 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 6/13/2023 Approved THOMAS LOGRASSO
Sewer 7/25/2023 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 9/8/2023 Approved THOMAS LOGRASSO
Final 9/8/2023 Corrections Issued THOMAS LOGRASSO
Green Building Final 9/8/2023 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 9/8/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 9/8/2023 Not Required THOMAS LOGRASSO
Smoke Detectors 9/8/2023 Approved THOMAS LOGRASSO
Final 10/17/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 11/16/2023 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 11/16/2023 Approved THOMAS LOGRASSO