11337 W UTOPIA AVE 90230
Certificate Information: 11337 W UTOPIA AVE 90230
- Application / Permit
- 23010-10000-01566
- Plan Check / Job No.
- B23LA06681
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY DETACHED ADU.
- Permit Issued
- Issued on 6/20/2023
- Issuing Office
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | JOE VO |
| Corrections Issued | 4/18/2023 | JOE VO |
| Quality Review Completed | 4/18/2023 | GARO TELMI |
| Plan Check Approved | 6/20/2023 | JOE VO |
| Issued | 6/20/2023 | APPLICANT |
| CofO in Progress | 3/4/2024 | RICHARD STEINBACH |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
| CofO Issued | 3/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2023 | DINAH GARIN |
| Sewer availability | Cleared | 4/21/2023 | DINAH GARIN |
| Specific Plan | Cleared | 4/21/2023 | JIMMY VIVAR |
| Roof/Waste drainage to street | Cleared | 5/3/2023 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 5/9/2023 | KURT CORRAL |
| Construction near power lines | Cleared | 6/20/2023 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/2/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/11/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/25/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 9/25/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| MERV13>=Rough | 9/25/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/25/2023 | Partial Approval | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 9/25/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 10/30/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 11/6/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 11/6/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/6/2023 | Approved | JESUS RODRIGUEZ |
| Sewer | 11/6/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 11/14/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 11/14/2023 | Approved | TEMISTOCLES CAAL |
| Insulation | 11/21/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 11/27/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 12/7/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| Final | 2/29/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| MERV13>=Final | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| MERV13>=Rough | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 2/29/2024 | Approved | JESUS RODRIGUEZ |