2206 S RIDGELEY DR 90016
Certificate Information: 2206 S RIDGELEY DR 90016
- Application / Permit
- 23010-10000-01560
- Plan Check / Job No.
- B23LA06669
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- NEW DETACHED STORAGE SHED PER ENGINEER DESIGN
- Permit Issued
- Issued on 8/18/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2023 | APPLICANT |
| Building Plans Picked Up | 4/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | KHUONG TRUONG |
| Corrections Issued | 4/20/2023 | KHUONG TRUONG |
| Plan Check Approved | 8/18/2023 | SAMUEL GONZALEZ |
| Issued | 8/18/2023 | APPLICANT |
| CofO in Progress | 10/10/2024 | JUSTIN HAWLEY |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
| CofO Issued | 10/16/2024 | RUBEN SALAS |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
Permit Application Clearance Information
| ZA Case | Cleared | 6/20/2023 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2023 | HUGO LOPEZ |
| Low Impact Development (LID) | Cleared | 8/11/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 8/12/2023 | HUGO LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dong,, Truong Tan; Lic. No.: C75466 | 10692 SILVER CIRCLE GARDEN GROVE, CA 92843 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/16/2023 | Partial Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 11/15/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Conditional Approval | RONNIE MINDANAO |
| Deputy Wood Construction | 12/14/2023 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 2/28/2024 | Approved | STUART CHAPMAN |
| Final | 2/28/2024 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 2/28/2024 | Not Required | STUART CHAPMAN |
| Smoke Detectors | 2/28/2024 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 2/28/2024 | Approved | STUART CHAPMAN |
| Final | 7/11/2024 | Corrections Issued | ARTHUR NEGRETE |
| ELECTRICAL-Final | 10/10/2024 | Approved | JUSTIN HAWLEY |
| Final | 10/10/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 10/10/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 10/10/2024 | Approved | JUSTIN HAWLEY |