5438 S 3RD AVE 90043
Certificate Information: 5438 S 3RD AVE 90043
- Application / Permit
- 23010-10000-01528
- Plan Check / Job No.
- B23LA06564
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2 STORY DETACHED ACCESSORY DWELLIN UNIT WITH ATTACHED TRELLIS PER ORDINANCE LAMC 12.22 A.33 (c)&(d)
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | JAD BASMA |
| Corrections Issued | 5/16/2023 | JAD BASMA |
| Quality Review Completed | 5/23/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 6/13/2023 | APPLICANT |
| Applicant returned to address corrections | 3/22/2024 | JAD BASMA |
| Applicant returned to address corrections | 5/30/2024 | JAD BASMA |
| Plan Check Approved | 7/25/2024 | JAD BASMA |
| Issued | 11/21/2024 | APPLICANT |
| CofO in Progress | 6/10/2025 | LUIS CASTRO |
| Permit Finaled | 6/11/2025 | DEROLD HAUFF |
| CofO Issued | 6/11/2025 | DEROLD HAUFF |
| Permit Finaled | 6/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2023 | TERRY PHAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2023 | TERRY PHAN |
| Sewer availability | Cleared | 9/1/2023 | TERRY PHAN |
| Low Impact Development (LID) | Cleared | 3/4/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 3/7/2024 | TERRY PHAN |
Contact Information
| Contractor | Superdry Restoration Inc; Lic. No.: 973252-B | 6476 FLORENCE AVE STE A BELL GARDENS, CA 90201 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/7/2025 | Not Ready for Inspection | LUIS CASTRO |
| Underground Mechanical | 1/7/2025 | Partial Approval | LUIS CASTRO |
| Footing/Foundation/Slab | 1/13/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 2/5/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2025 | Approved | LUIS CASTRO |
| Shower Pan | 2/7/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 2/11/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 2/11/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 2/11/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 2/11/2025 | Partial Approval | LUIS CASTRO |
| Interior/Exterior Lathing | 2/11/2025 | Partial Approval | LUIS CASTRO |
| Verify Sprinkler Sign Off | 2/11/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 2/13/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 2/13/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 2/13/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 2/14/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 2/14/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 2/21/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 2/25/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 3/5/2025 | Approved | LUIS CASTRO |
| Service/Power Release | 3/26/2025 | Corrections Issued | LUIS CASTRO |
| Sewer | 4/7/2025 | Approved | LUIS CASTRO |
| Underground Mechanical | 4/7/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/21/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 4/21/2025 | Approved | LUIS CASTRO |
| Final | 4/21/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 4/21/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 4/21/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 4/21/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/21/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Not Required | LUIS CASTRO |
| Service/Power Release | 4/21/2025 | Not Ready for Inspection | LUIS CASTRO |
| Smoke Detectors | 4/21/2025 | Approved | LUIS CASTRO |
| Final | 5/16/2025 | Not Ready for Inspection | LUIS CASTRO |
| Service/Power Release | 5/16/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 5/20/2025 | Partial Inspection | LUIS CASTRO |
| Final | 6/10/2025 | OK to Issue CofO | LUIS CASTRO |
| Service/Power Release | 6/10/2025 | Approved | LUIS CASTRO |