5337 N SUNNYSLOPE AVE 91401

Certificate Information: 5337 N SUNNYSLOPE AVE 91401

Application / Permit
23010-10000-01520
Plan Check / Job No.
B23LA05968
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*eplan* PROPOSED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 7/25/2023
Issuing Office
Current Status
CofO Issued on 7/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 SINA KHOSRAVI
Corrections Issued 4/11/2023 SINA KHOSRAVI
Quality Review Completed 4/15/2023 GARO TELMI
Applicant returned to address corrections 6/27/2023 SINA KHOSRAVI
Plan Check Approved 7/25/2023 SINA KHOSRAVI
Issued 7/25/2023 APPLICANT
CofO in Progress 6/14/2024 MISAEL ESPARZA
Permit Finaled 7/2/2024 RUBEN SALAS
CofO Issued 7/2/2024 RUBEN SALAS
Permit Finaled 7/2/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/18/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 4/24/2023 NIKKI ZULUETA
Sewer availability Cleared 4/24/2023 NIKKI ZULUETA
Construction near power lines Cleared 6/12/2023 OSCAR CASTRO
Construction within easement Cleared 6/12/2023 OSCAR CASTRO
Low Impact Development (LID) Cleared 6/12/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/12/2023 LEE GUILBEAUX
Hydrant and Access approval Cleared 6/15/2023 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/25/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/7/2023 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Corrections Issued MISAEL ESPARZA
HVAC-Rough 10/17/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 10/17/2023 Approved MISAEL ESPARZA
ELECTRICAL-Rough 10/20/2023 Corrections Issued MISAEL ESPARZA
Shower Pan 10/20/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 10/25/2023 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/31/2023 Approved MISAEL ESPARZA
ELECTRICAL-Rough 10/31/2023 Approved MISAEL ESPARZA
Insulation 10/31/2023 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 10/31/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/3/2023 Not Ready for Inspection MISAEL ESPARZA
Insulation 11/9/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/9/2023 Partial Approval MISAEL ESPARZA
Drywall Nailing 11/16/2023 Approved JUAN VALENZUELA
PLUMBING-Final 3/4/2024 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 3/15/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 3/21/2024 Approved MISAEL ESPARZA
HVAC-Final 3/21/2024 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 4/1/2024 Approved MISAEL ESPARZA
Final 4/1/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 4/1/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 4/1/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 4/1/2024 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 4/1/2024 Approved MISAEL ESPARZA
Final 4/5/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 4/5/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 4/5/2024 Not Ready for Inspection MISAEL ESPARZA
Final 4/9/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 4/9/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/9/2024 SGSOV Not Required MISAEL ESPARZA
Service/Power Release 4/9/2024 Not Ready for Inspection MISAEL ESPARZA
Final 4/16/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 4/16/2024 Not Ready for Inspection MISAEL ESPARZA
Service/Power Release 4/16/2024 Not Ready for Inspection MISAEL ESPARZA
Final 6/12/2024 OK to Issue CofO MISAEL ESPARZA
Green Building Final 6/12/2024 Approved MISAEL ESPARZA
Service/Power Release 6/12/2024 Approved MISAEL ESPARZA