5337 N SUNNYSLOPE AVE 91401
Certificate Information: 5337 N SUNNYSLOPE AVE 91401
- Application / Permit
- 23010-10000-01520
- Plan Check / Job No.
- B23LA05968
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *eplan* PROPOSED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 7/25/2023
- Issuing Office
- Current Status
- CofO Issued on 7/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2023 | SINA KHOSRAVI |
| Corrections Issued | 4/11/2023 | SINA KHOSRAVI |
| Quality Review Completed | 4/15/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/27/2023 | SINA KHOSRAVI |
| Plan Check Approved | 7/25/2023 | SINA KHOSRAVI |
| Issued | 7/25/2023 | APPLICANT |
| CofO in Progress | 6/14/2024 | MISAEL ESPARZA |
| Permit Finaled | 7/2/2024 | RUBEN SALAS |
| CofO Issued | 7/2/2024 | RUBEN SALAS |
| Permit Finaled | 7/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 4/24/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 6/12/2023 | OSCAR CASTRO |
| Construction within easement | Cleared | 6/12/2023 | OSCAR CASTRO |
| Low Impact Development (LID) | Cleared | 6/12/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/12/2023 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 6/15/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/25/2023 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/7/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 10/17/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/17/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/20/2023 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 10/20/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/31/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/31/2023 | Approved | MISAEL ESPARZA |
| Insulation | 10/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 10/31/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/3/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 11/9/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/9/2023 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 11/16/2023 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 3/4/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 3/15/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 3/21/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 3/21/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/1/2024 | Approved | MISAEL ESPARZA |
| Final | 4/1/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 4/1/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 4/1/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 4/1/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 4/1/2024 | Approved | MISAEL ESPARZA |
| Final | 4/5/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 4/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 4/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 4/9/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 4/9/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Not Required | MISAEL ESPARZA |
| Service/Power Release | 4/9/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 4/16/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 4/16/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 4/16/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 6/12/2024 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 6/12/2024 | Approved | MISAEL ESPARZA |
| Service/Power Release | 6/12/2024 | Approved | MISAEL ESPARZA |