4248 S NEOSHO AVE 90066

Certificate Information: 4248 S NEOSHO AVE 90066

Application / Permit
23010-10000-01510
Plan Check / Job No.
B23LA06461
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ADU AT REAR OF LOT
Permit Issued
Issued on 7/14/2023
Issuing Office
Current Status
CofO Issued on 12/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/10/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 JOE VO
Corrections Issued 4/15/2023 JOE VO
Quality Review Completed 4/16/2023 PRANITA SHAH
Plan Check Approved 7/12/2023 JOE VO
Issued 7/14/2023 APPLICANT
CofO in Progress 11/19/2024 MICHAEL ALLEN
Permit Finaled 12/31/2024 RICHARD STEINBACH
CofO Issued 12/31/2024 RICHARD STEINBACH
Permit Finaled 12/31/2024 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 4/19/2023 OSCAR CASTRO
Address approval Cleared 4/20/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 4/20/2023 DARIN LAM
Sewer availability Cleared 4/20/2023 DARIN LAM
Hydrant and Access approval Cleared 4/28/2023 KURT CORRAL
Specific Plan Cleared 6/5/2023 PEDRO AYALA
Low Impact Development Cleared 6/27/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 6/28/2023 DARIN LAM

Contact Information

Contractor Wetzel Homes Inc; Lic. No.: 1058085-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/1/2023 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 8/22/2023 Corrections Issued HERBERT GIRON
Special/Order Compliance 8/22/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 8/30/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 11/27/2023 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 11/27/2023 Partial Approval TEMISTOCLES CAAL
Sewer 11/27/2023 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/10/2024 Partial Approval BOBBY KEY
HVAC-Rough 1/10/2024 Approved BOBBY KEY
PLUMBING-Rough 1/10/2024 Approved BOBBY KEY
Special/Order Compliance 1/10/2024 Partial Inspection BEN MOLSTAD
BUILDING-Rough-Frame 1/12/2024 Corrections Issued TEMISTOCLES CAAL
Deputy Wood Construction 1/12/2024 No Access for Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 1/12/2024 Not Ready for Inspection TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Approved TEMISTOCLES CAAL
Green Building Rough 1/12/2024 Corrections Issued TEMISTOCLES CAAL
Verify Sprinkler Sign Off 1/12/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Rough 1/17/2024 Partial Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 2/1/2024 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 3/15/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 3/15/2024 Approved TEMISTOCLES CAAL
Green Building Rough 3/15/2024 Approved TEMISTOCLES CAAL
Insulation 3/15/2024 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 3/15/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 3/27/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 3/27/2024 Approved TEMISTOCLES CAAL
Shower Pan 4/16/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 8/16/2024 SGSOV Not Ready TEMISTOCLES CAAL
ELECTRICAL-Final 8/23/2024 Approved TEMISTOCLES CAAL
Final 8/23/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 8/23/2024 Approved TEMISTOCLES CAAL
HVAC-Final 8/23/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 8/23/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Not Required TEMISTOCLES CAAL
Service/Power Release 8/23/2024 Corrections Issued TEMISTOCLES CAAL
Smoke Detectors 8/23/2024 Approved TEMISTOCLES CAAL
Final 10/30/2024 Corrections Issued BOBBY KEY
Final 11/5/2024 No Access for Inspection MICHAEL ALLEN
Service/Power Release 11/5/2024 Corrections Issued MICHAEL ALLEN
ELECTRICAL-Final 11/7/2024 Corrections Issued MICHAEL ALLEN
Final 11/7/2024 Corrections Issued MICHAEL ALLEN
Service/Power Release 11/7/2024 Not Ready for Inspection MICHAEL ALLEN
Special/Order Compliance 11/7/2024 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 11/18/2024 Approved MICHAEL ALLEN
Final 11/18/2024 OK to Issue CofO MICHAEL ALLEN
Service/Power Release 11/18/2024 Approved MICHAEL ALLEN