20915 S DALTON AVE 90501
Certificate Information: 20915 S DALTON AVE 90501
- Application / Permit
- 23010-10000-01508
- Plan Check / Job No.
- B23LA06458
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 11/16/2023
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | DANIEL YIP |
| Corrections Issued | 5/2/2023 | DANIEL YIP |
| Quality Review Completed | 5/2/2023 | GARO TELMI |
| Plan Check Approved | 8/25/2023 | DANIEL YIP |
| Issued | 11/16/2023 | APPLICANT |
| CofO in Progress | 6/3/2025 | ANSON MAGLASANG |
| Permit Finaled | 6/3/2025 | ANSON MAGLASANG |
| CofO Issued | 6/3/2025 | ANSON MAGLASANG |
| Permit Finaled | 6/3/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 6/6/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2023 | ANA SORIANO |
| Miscellaneous | Cleared | 6/13/2023 | ANA SORIANO |
| Sewer availability | Cleared | 7/21/2023 | ANA SORIANO |
| Low Impact Development (LID) | Cleared | 8/11/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 8/17/2023 | ANA SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/18/2024 | Partial Approval | EUGENE CASSIDY |
| Service/Power Release | 1/18/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 1/30/2024 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/15/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/27/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 8/27/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/27/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/12/2024 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 9/12/2024 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 9/12/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 9/25/2024 | Approved | EUGENE CASSIDY |
| Shower Pan | 9/25/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 10/2/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/2/2024 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/21/2024 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 1/7/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/16/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/16/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 4/16/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/16/2025 | Approved | EUGENE CASSIDY |
| HVAC-Final | 4/16/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 4/16/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/16/2025 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 4/16/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 4/16/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/30/2025 | Approved | EUGENE CASSIDY |
| Final | 4/30/2025 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 4/30/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 6/2/2025 | OK to Issue CofO | EUGENE CASSIDY |