4140 N SUNNYSLOPE AVE 91423
Certificate Information: 4140 N SUNNYSLOPE AVE 91423
- Application / Permit
- 23010-10000-01507
- Plan Check / Job No.
- B23LA06455
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) TWO STORY SFD W/ ATTACHED TWO CAR GARAGE
- Permit Issued
- Issued on 9/28/2023
- Issuing Office
- Current Status
- CofO Issued on 2/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 4/26/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 5/1/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 9/1/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 9/26/2023 | SERGIO GUTIERREZ |
| Issued | 9/28/2023 | APPLICANT |
| CofO in Progress | 2/3/2026 | JOSE AVILA |
| Permit Finaled | 2/9/2026 | RUBEN SALAS |
| CofO Issued | 2/9/2026 | RUBEN SALAS |
| Permit Finaled | 2/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 8/14/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 8/15/2023 | MELINEH AGHAKHABIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2023 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 8/23/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 8/23/2023 | TAL SHEMEN |
| Permit | Cleared | 9/14/2023 | TAL SHEMEN |
| GPI Written Notices | Cleared | 9/26/2023 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 9/26/2023 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abrahamian,, Thomas; Lic. No.: L9689 | 712 FAY DRIVE GLENDALE, CA 91206 |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| DANIEL ORRANTE, (818) 374-1157 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/6/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 10/6/2023 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/24/2024 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 5/29/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/3/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/7/2024 | Approved | JOSE AVILA |
| Deputy Wood Construction | 6/18/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 8/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 8/12/2024 | Partial Inspection | JUAN VALENZUELA |
| Shower Pan | 8/20/2024 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 8/23/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 8/23/2024 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 8/27/2024 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 8/27/2024 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/29/2024 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/30/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 8/30/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/5/2024 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 9/5/2024 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 9/5/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 9/9/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 9/12/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Insulation | 9/13/2024 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 9/13/2024 | Approved | JOSE AVILA |
| Deputy Wood Construction | 9/20/2024 | Partial Approval | JOSE AVILA |
| Drywall Nailing | 9/20/2024 | Approved | JOSE AVILA |
| HVAC-Final | 1/29/2025 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 1/29/2025 | Partial Inspection | JUAN VALENZUELA |
| HVAC-Final | 2/12/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/18/2025 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 2/27/2025 | Approved | JOSE AVILA |
| HVAC-Final | 2/27/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/27/2025 | SGSOV No Gas | JOSE AVILA |
| Final | 4/16/2025 | Corrections Issued | JOSE AVILA |
| Green Building Final | 4/16/2025 | Approved | JOSE AVILA |
| Service/Power Release | 4/16/2025 | Approved | JOSE AVILA |
| Smoke Detectors | 4/16/2025 | Approved | JOSE AVILA |
| Final | 4/23/2025 | Not Ready for Inspection | JOSE AVILA |
| Final | 7/25/2025 | Corrections Issued | JOSE AVILA |
| Final | 1/27/2026 | Corrections Issued | JOSE AVILA |
| Final | 2/3/2026 | OK to Issue CofO | JOSE AVILA |