7011 N BALCOM AVE 91335
Certificate Information: 7011 N BALCOM AVE 91335
- Application / Permit
- 23010-10000-01498
- Plan Check / Job No.
- B23LA06427
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN New detached ADU (42'9" x 28'0") per LAMC 12.22 A.33 (c)-(d). All work done per WFPP. ***SEE COMMENTS***
- Permit Issued
- Issued on 4/29/2024
- Issuing Office
- Current Status
- Issued on 4/29/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2023 | DANIEL SMILEY |
| Corrections Issued | 4/18/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 4/15/2024 | DANIEL SMILEY |
| Applicant returned to address corrections | 4/18/2024 | NGHI SU |
| Plan Check Approved | 4/21/2024 | NGHI SU |
| Issued | 4/29/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 9/9/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/9/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/6/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 3/25/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 3/26/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/10/2024 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 10/25/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Approved | ARUTYUN MADATYAN |
| Wood Frame | 11/13/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Gas Test | 2/12/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Pool/Spa Cover | 2/12/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| Gas Test | 2/19/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 4/24/2025 | Corrections Issued | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 4/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 4/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 4/24/2025 | Corrections Issued | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 4/28/2025 | Partial Approval | ARUTYUN MADATYAN |
| Green Building Rough | 4/28/2025 | Approved | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 4/28/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 4/30/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 6/16/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 6/16/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Shower Pan | 6/16/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 7/16/2025 | Approved | GEVORK IPCHYAN |
| Shower Pan | 7/16/2025 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 12/2/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 12/8/2025 | Corrections Issued | JUAN ALVARADO |
| HVAC-Final | 12/8/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 12/8/2025 | Approved | JUAN ALVARADO |