332 1/2-334 1/2 S AVENUE 19 90031
Certificate Information: 332 1/2-334 1/2 S AVENUE 19 90031
- Application / Permit
- 23010-10000-01466
- Plan Check / Job No.
- B23LA06144
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: (N) DETACHED TWO-UNIT 2-STORY ADU WITH ATTADCHED REC ROOM PER CA GOVT. CODE 65852.2 (e)(1)(D) AND APPLICABLE PART OF LAMC 12.22 A.33(c)-(d), (g).
- Permit Issued
- Issued on 8/8/2023
- Issuing Office
- Current Status
- CofO Issued on 8/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 5/6/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 5/15/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 6/27/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 7/6/2023 | MAHNAZ NOURHASHEMI |
| Issued | 8/8/2023 | APPLICANT |
| CofO in Progress | 7/12/2024 | OSVALDO PARAMO |
| Permit Finaled | 8/8/2024 | DEROLD HAUFF |
| CofO Issued | 8/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2023 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 5/31/2023 | HUGO LOPEZ |
| Hydrant and Access approval | Cleared | 6/23/2023 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 6/29/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 7/10/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | Ponderosa Pines Gen Contractors; Lic. No.: 450947-B | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
| Engineer | Salto,, Alvaro; Lic. No.: NA83859 | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/23/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Underground Mechanical | 8/23/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 8/28/2023 | Conditional Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/30/2023 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/17/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 1/9/2024 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/5/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 3/5/2024 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 3/5/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/7/2024 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 3/7/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 3/7/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/12/2024 | Approved | OSVALDO PARAMO |
| Insulation | 3/27/2024 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 4/3/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 6/18/2024 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 6/25/2024 | Approved | OSVALDO PARAMO |
| Gas Test | 6/28/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 6/28/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 6/28/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/2/2024 | Conditional Approval | OSVALDO PARAMO |
| MERV13>=Final | 7/2/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 7/2/2024 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 7/2/2024 | Approved | OSVALDO PARAMO |
| Final | 7/11/2024 | OK to Issue CofO | OSVALDO PARAMO |