2032 E JUDSON ST 90033

Certificate Information: 2032 E JUDSON ST 90033

Application / Permit
23010-10000-01454
Plan Check / Job No.
B23LA06083
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. CONVER EXISTING STORAGE BUILDING INTO ADU WITH ADDDITION. PROPOSED ATTACHED COVERED PATIO (60 SF) AND PROPOSED ROOFTOP DECK.
Permit Issued
Issued on 8/19/2025
Issuing Office
Current Status
CofO Issued on 4/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 CRYSTEL MAALOUF
Corrections Issued 5/5/2023 CRYSTEL MAALOUF
Quality Review Completed 5/18/2023 FARUK SEZER
Applicant returned to address corrections 2/1/2024 CRYSTEL MAALOUF
Applicant returned to address corrections 2/2/2024 CRYSTEL MAALOUF
Applicant returned to address corrections 7/10/2024 CRYSTEL MAALOUF
Applicant returned to address corrections 6/18/2025 CRYSTEL MAALOUF
Plan Check Approved 8/18/2025 CRYSTEL MAALOUF
Issued 8/19/2025 APPLICANT
CofO in Progress 4/20/2026 ALIZAH MAYAGOITIA
CofO Issued 4/23/2026 DEROLD HAUFF
Permit Finaled 4/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/14/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 3/14/2024 TREVOR QUAN
Construction within easement Cleared 10/7/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 7/8/2025 TREVOR QUAN
Sewer availability Cleared 7/8/2025 TREVOR QUAN
GPI Written Notices Cleared 8/18/2025 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 8/18/2025 RAMAZANALI ALMASI

Contact Information

Contractor Owner-Builder       ,
Engineer Badilla, Garces, Maria Elena; Lic. No.: C81817 945 N GLENN AVE      ONTARIO, CA 91764

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/30/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/3/2025 Approved ALIZAH MAYAGOITIA
METHANE-Barrier 10/3/2025 Approved ALIZAH MAYAGOITIA
METHANE-Subgrade 10/3/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 10/15/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 10/15/2025 Approved ALIZAH MAYAGOITIA
METHANE-Rough 10/15/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 10/15/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 10/15/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/23/2025 Corrections Issued GEM DE OCAMPO
BUILDING-Rough-Frame 10/27/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 10/29/2025 Approved ANTHONY RAMOS
Insulation 10/29/2025 Approved ANTHONY RAMOS
Drywall Nailing 11/4/2025 Corrections Issued GEM DE OCAMPO
Drywall Nailing 11/6/2025 Approved ALIZAH MAYAGOITIA
Final 2/6/2026 Corrections Issued ALIZAH MAYAGOITIA
MERV13>=Final 2/6/2026 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 2/6/2026 Approved ALIZAH MAYAGOITIA
Final 2/27/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 4/15/2026 Conditional Approval ALIZAH MAYAGOITIA
Final 4/20/2026 OK to Issue CofO ALIZAH MAYAGOITIA