946 1/2 N LUCILE AVE 90026
Certificate Information: 946 1/2 N LUCILE AVE 90026
- Application / Permit
- 23010-10000-01444
- Plan Check / Job No.
- B23LA06050
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT AT REAR PER LAMC 12.22 A.33(c) AND (d) FULLY SPRINKLERED
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Current Status
- CofO Issued on 3/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2023 | JOE VO |
| Corrections Issued | 4/22/2023 | JOE VO |
| Quality Review Completed | 5/1/2023 | GARO TELMI |
| Plan Check Approved | 6/27/2023 | JOE VO |
| Issued | 6/27/2023 | APPLICANT |
| CofO in Progress | 3/18/2025 | FREDDIE RIVERA |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
| CofO Issued | 3/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/27/2023 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 4/27/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2023 | JEANIE LAM |
| Sewer availability | Cleared | 4/27/2023 | JEANIE LAM |
| Low Impact Development (LID) | Cleared | 5/11/2023 | MARCO SANCHEZ |
| Miscellaneous | Cleared | 5/15/2023 | ALBERT TAM |
| Roof/Waste drainage to street | Cleared | 5/16/2023 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 5/17/2023 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kang,, Danniel; Lic. No.: S6242 | 1176 N KNOLLWOOD CT ANAHEIM, CA 92801 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2023 | Approved | FREDDIE RIVERA |
| Deputy Reinf. Concrete | 9/29/2023 | Partial Approval | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 10/3/2023 | Partial Approval | FREDDIE RIVERA |
| Deputy Reinf. Concrete | 11/6/2023 | Conditional Approval | FREDDIE RIVERA |
| Deputy Reinf. Concrete | 11/17/2023 | Conditional Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 12/6/2023 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/6/2023 | Partial Inspection | FREDDIE RIVERA |
| Deputy Wood Construction | 12/13/2023 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 12/13/2023 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Approved | FREDDIE RIVERA |
| Deputy Wood Construction | 1/8/2024 | Conditional Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Partial Approval | FREDDIE RIVERA |
| Deputy Wood Construction | 1/12/2024 | Conditional Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 1/18/2024 | Approved | FREDDIE RIVERA |
| Deputy Wood Construction | 1/25/2024 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/25/2024 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 1/25/2024 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/29/2024 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 1/29/2024 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/31/2024 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 1/31/2024 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 1/31/2024 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/14/2024 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 2/14/2024 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/16/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 2/16/2024 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 2/16/2024 | Approved | FREDDIE RIVERA |
| Insulation | 3/11/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 3/11/2024 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 3/14/2024 | Approved | FREDDIE RIVERA |
| Shower Pan | 4/23/2024 | Corrections Issued | FREDDIE RIVERA |
| Shower Pan | 4/24/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/26/2024 | Approved | SCOTT FINNILA |
| Masonry Wall/Backfill | 9/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Underground Mechanical | 9/23/2024 | Approved | FREDDIE RIVERA |
| Service/Power Release | 12/6/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 12/19/2024 | Approved | FREDDIE RIVERA |
| HVAC-Final | 1/10/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 1/17/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 2/7/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/7/2025 | Approved | FREDDIE RIVERA |
| Green Building Final | 2/7/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 2/7/2025 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 2/7/2025 | Approved | FREDDIE RIVERA |
| Final | 3/3/2025 | OK to Issue CofO | FREDDIE RIVERA |
| Service/Power Release | 3/3/2025 | Approved | FREDDIE RIVERA |