519 S 26TH ST 90049

Certificate Information: 519 S 26TH ST 90049

Application / Permit
23010-10000-01432
Plan Check / Job No.
B23LA05956
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 49'-6"x20'-0" 1-story Accessory Dwelling unit 856 sq ft PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 9/29/2023
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2023 APPLICANT
Assigned to Plan Check Engineer 4/11/2023 OMAR GARNICA
Corrections Issued 4/12/2023 OMAR GARNICA
Applicant returned to address corrections 8/14/2023 KAMYAR EMAMI
Plan Check Approved 9/22/2023 KAMYAR EMAMI
Issued 9/29/2023 APPLICANT
CofO in Progress 10/3/2025 MEL KHACHATOURIAN
Permit Finaled 10/7/2025 RICHARD STEINBACH
CofO Issued 10/7/2025 RICHARD STEINBACH
Permit Finaled 10/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/26/2023 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 4/26/2023 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 4/27/2023 LIAM ODONOVAN
Sewer availability Cleared 4/27/2023 LIAM ODONOVAN
Specific Plan Cleared 5/3/2023 JIMMY VIVAR
Low Impact Development (LID) Cleared 7/11/2023 LUIS LUVANO
Construction near power lines Cleared 8/6/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Herrera,, Edgar E; Lic. No.: NA67603       ,

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/13/2023 Off-Hour Fees Due
PLUMBING-Rough 11/13/2023 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 11/14/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 11/14/2023 Off-Hour Fees Due
PLUMBING-Rough 11/14/2023 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 11/14/2023 Off-Hour Fees Due
PLUMBING-Rough 11/15/2023 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 11/21/2023 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 11/22/2023 Approved OGANES TARAKHCHYAN
Wood Frame 12/15/2023 Off-Hour Fees Due
Wood Frame 12/15/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 1/17/2024 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 1/25/2024 Not Ready for Inspection BEN MOLSTAD
Gas Test 1/25/2024 Approved BEN MOLSTAD
Green Building Rough 1/25/2024 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 1/25/2024 Approved BEN MOLSTAD
Verify Sprinkler Sign Off 1/25/2024 Not Ready for Inspection BEN MOLSTAD
Sewer 1/26/2024 Approved BEN MOLSTAD
Underground Mechanical 1/26/2024 Approved BEN MOLSTAD
ELECTRICAL-Rough 2/27/2024 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 2/27/2024 Approved STEPHANIE SWANSON
Green Building Rough 2/27/2024 Not Ready for Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 3/8/2024 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 3/8/2024 Approved ASHLEY THOMPSON
Green Building Rough 3/8/2024 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Rough 3/8/2024 Corrections Issued ASHLEY THOMPSON
Underground Mechanical 3/8/2024 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 3/12/2024 Approved TEMISTOCLES CAAL
Green Building Rough 3/12/2024 Approved TEMISTOCLES CAAL
HVAC-Rough 3/12/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 3/12/2024 Partial Approval TEMISTOCLES CAAL
Insulation 3/15/2024 Corrections Issued OGANES TARAKHCHYAN
Insulation 3/19/2024 Approved CARLOS MATAMOROS
Drywall Nailing 3/26/2024 Partial Approval HERBERT GIRON
Drywall Nailing 4/9/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 4/9/2024 Not Ready for Inspection JESUS PINEDA
Interior/Exterior Lathing 4/16/2024 Partial Approval OGANES TARAKHCHYAN
Shower Pan 4/17/2024 Approved MEL KHACHATOURIAN
Final 4/30/2025 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 4/30/2025 Approved KIRK SANDERS
Green Building Final 4/30/2025 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Approved KIRK SANDERS
Service/Power Release 4/30/2025 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 4/30/2025 Approved KIRK SANDERS
ELECTRICAL-Final 10/2/2025 Approved MEL KHACHATOURIAN
Final 10/2/2025 OK to Issue CofO MEL KHACHATOURIAN
Green Building Final 10/2/2025 Approved MEL KHACHATOURIAN
Service/Power Release 10/2/2025 Approved MEL KHACHATOURIAN