2845-2845 1/2 N MARSH ST 90039
Certificate Information: 2845-2845 1/2 N MARSH ST 90039
- Application / Permit
- 23010-10000-01428
- Plan Check / Job No.
- B23LA05931
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY, 2 UNIT ADU (DETACHED DUPLEX UNDER SEPARATE PERMIT) PER LAMC 12.22 A(33)(c) - (d) AND (g) AND GOVT. CODE 65852.2(e)(1)(D). NFPA-13D FIRE SPRINKLER SYSTEM ARE REQUIRED.
- Permit Issued
- Issued on 10/18/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2023 | NGHI SU |
| Corrections Issued | 4/10/2023 | NGHI SU |
| Quality Review Completed | 4/14/2023 | KEN GILL |
| Building Plans Picked Up | 4/18/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 4/28/2023 | APPLICANT |
| Plan Check Approved | 8/30/2023 | NGHI SU |
| Issued | 10/18/2023 | APPLICANT |
| CofO in Progress | 12/9/2024 | LUIS CASTRO |
| CofO Issued | 12/18/2024 | DEROLD HAUFF |
| Permit Finaled | 12/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 5/18/2023 | JAZMIN ROQUE |
| Address approval | Cleared | 5/19/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 5/30/2023 | TREVOR QUAN |
| Low Impact Development (LID) | Cleared | 6/2/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 6/11/2023 | AHMED AMARRAGY |
| Hydrant and Access approval | Cleared | 7/21/2023 | MATTHEW CRAIG |
| SB8 RUD | Cleared | 8/15/2023 | SAMANTHA RIVERA |
| ZI | Cleared | 8/21/2023 | DAVID URITA |
Contact Information
| Architect | , ; Lic. No.: C34496 | 9856 VIDOR DRIVE LOS ANGELES, CA 90035 |
| Contractor | Owner-Builder | , |
| Engineer | Bermejo,, Gil Banzon; Lic. No.: C86264 | 2308 MOUNTAIN OAK RD BAKERSFIELD, CA 93311 |
| Engineer | Pinzon,, Eduardo Andres; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Service/Power Release | 10/24/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 10/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Sewer | 12/8/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Underground Mechanical | 12/8/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Underground Mechanical | 12/12/2023 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 12/18/2023 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 1/25/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Steel/Welding | 2/9/2024 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/12/2024 | Approved | THOMAS LOGRASSO |
| Deputy Steel/Welding | 3/21/2024 | Conditional Approval | THOMAS LOGRASSO |
| Sewer | 3/22/2024 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 4/22/2024 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 5/13/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 5/13/2024 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 5/14/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Partial Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/31/2024 | Partial Inspection | SCOTT FINNILA |
| HVAC-Rough | 6/4/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/6/2024 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 6/6/2024 | Corrections Issued | JEFFREY MEAD |
| MERV13>=Rough | 6/6/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 6/6/2024 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 6/13/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 6/13/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/13/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Rough | 6/13/2024 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 6/13/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/18/2024 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 6/20/2024 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 6/25/2024 | Approved | WILLIAM KUEHN |
| HVAC-Rough | 6/25/2024 | Approved | WILLIAM KUEHN |
| Insulation | 6/25/2024 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 7/9/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Drywall Nailing | 7/11/2024 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 8/5/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 8/7/2024 | Approved | ANTHONY RAMOS |
| Final | 11/7/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Gas Test | 11/7/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 11/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Final | 11/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 11/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 11/21/2024 | Corrections Issued | WILLIAM SIERRA |
| Gas Test | 11/21/2024 | Approved | WILLIAM SIERRA |
| Green Building Final | 11/21/2024 | Corrections Issued | WILLIAM SIERRA |
| MERV13>=Final | 11/21/2024 | Approved | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Approved | WILLIAM SIERRA |
| Service/Power Release | 11/21/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Smoke Detectors | 11/21/2024 | Approved | WILLIAM SIERRA |
| Final | 11/27/2024 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 11/27/2024 | Approved | WILLIAM SIERRA |
| Service/Power Release | 11/27/2024 | Approved | WILLIAM SIERRA |
| Special/Order Compliance | 12/5/2024 | Approved | LUIS CASTRO |
| Final | 12/9/2024 | OK to Issue CofO | LUIS CASTRO |