2845-2845 1/2 N MARSH ST 90039

Certificate Information: 2845-2845 1/2 N MARSH ST 90039

Application / Permit
23010-10000-01428
Plan Check / Job No.
B23LA05931
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY, 2 UNIT ADU (DETACHED DUPLEX UNDER SEPARATE PERMIT) PER LAMC 12.22 A(33)(c) - (d) AND (g) AND GOVT. CODE 65852.2(e)(1)(D). NFPA-13D FIRE SPRINKLER SYSTEM ARE REQUIRED.
Permit Issued
Issued on 10/18/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 NGHI SU
Corrections Issued 4/10/2023 NGHI SU
Quality Review Completed 4/14/2023 KEN GILL
Building Plans Picked Up 4/18/2023 APPLICANT
Disabled Access Plans Picked Up 4/28/2023 APPLICANT
Plan Check Approved 8/30/2023 NGHI SU
Issued 10/18/2023 APPLICANT
CofO in Progress 12/9/2024 LUIS CASTRO
CofO Issued 12/18/2024 DEROLD HAUFF
Permit Finaled 12/18/2024 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 5/18/2023 JAZMIN ROQUE
Address approval Cleared 5/19/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/30/2023 TREVOR QUAN
Sewer availability Cleared 5/30/2023 TREVOR QUAN
Low Impact Development (LID) Cleared 6/2/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 6/11/2023 AHMED AMARRAGY
Hydrant and Access approval Cleared 7/21/2023 MATTHEW CRAIG
SB8 RUD Cleared 8/15/2023 SAMANTHA RIVERA
ZI Cleared 8/21/2023 DAVID URITA

Contact Information

Architect , ; Lic. No.: C34496 9856 VIDOR DRIVE      LOS ANGELES, CA 90035
Contractor Owner-Builder       ,
Engineer Bermejo,, Gil Banzon; Lic. No.: C86264 2308 MOUNTAIN OAK RD      BAKERSFIELD, CA 93311
Engineer Pinzon,, Eduardo Andres; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Service/Power Release 10/24/2023 Not Ready for Inspection THOMAS LOGRASSO
Service/Power Release 10/27/2023 Not Ready for Inspection THOMAS LOGRASSO
Sewer 12/8/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Underground Mechanical 12/8/2023 Corrections Issued KATHRYN BUTTERWORTH
Underground Mechanical 12/12/2023 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 12/18/2023 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 1/25/2024 Not Ready for Inspection THOMAS LOGRASSO
Deputy Steel/Welding 2/9/2024 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 2/12/2024 Approved THOMAS LOGRASSO
Deputy Steel/Welding 3/21/2024 Conditional Approval THOMAS LOGRASSO
Sewer 3/22/2024 Approved THOMAS LOGRASSO
Underground Mechanical 4/22/2024 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 5/13/2024 Approved BRENDAN MORELLI
PLUMBING-Rough 5/13/2024 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 5/14/2024 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 5/31/2024 Partial Inspection SCOTT FINNILA
HVAC-Rough 6/4/2024 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/6/2024 Corrections Issued JEFFREY MEAD
HVAC-Rough 6/6/2024 Corrections Issued JEFFREY MEAD
MERV13>=Rough 6/6/2024 Not Ready for Inspection JEFFREY MEAD
Verify Sprinkler Sign Off 6/6/2024 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 6/13/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 6/13/2024 Approved HAMIK HARTOUNIAN
HVAC-Rough 6/13/2024 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Rough 6/13/2024 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 6/13/2024 Approved HAMIK HARTOUNIAN
HVAC-Rough 6/18/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 6/20/2024 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 6/25/2024 Approved WILLIAM KUEHN
HVAC-Rough 6/25/2024 Approved WILLIAM KUEHN
Insulation 6/25/2024 Approved WILLIAM KUEHN
Drywall Nailing 7/9/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Drywall Nailing 7/11/2024 Approved HAMIK HARTOUNIAN
Shower Pan 8/5/2024 Approved ANTHONY RAMOS
Interior/Exterior Lathing 8/7/2024 Approved ANTHONY RAMOS
Final 11/7/2024 Corrections Issued HAMIK HARTOUNIAN
Gas Test 11/7/2024 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 11/7/2024 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Final 11/7/2024 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/7/2024 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 11/7/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 11/7/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Final 11/21/2024 Corrections Issued WILLIAM SIERRA
Gas Test 11/21/2024 Approved WILLIAM SIERRA
Green Building Final 11/21/2024 Corrections Issued WILLIAM SIERRA
MERV13>=Final 11/21/2024 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Approved WILLIAM SIERRA
Service/Power Release 11/21/2024 Not Ready for Inspection WILLIAM SIERRA
Smoke Detectors 11/21/2024 Approved WILLIAM SIERRA
Final 11/27/2024 Corrections Issued WILLIAM SIERRA
Green Building Final 11/27/2024 Approved WILLIAM SIERRA
Service/Power Release 11/27/2024 Approved WILLIAM SIERRA
Special/Order Compliance 12/5/2024 Approved LUIS CASTRO
Final 12/9/2024 OK to Issue CofO LUIS CASTRO