1333 W 29TH ST 90007
Certificate Information: 1333 W 29TH ST 90007
- Application / Permit
- 23010-10000-01271
- Plan Check / Job No.
- B23LA05488
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan***PROPOSED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 8/9/2023
- Issuing Office
- Current Status
- CofO Issued on 11/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | SINA KHOSRAVI |
| Corrections Issued | 4/6/2023 | SINA KHOSRAVI |
| Quality Review Completed | 4/13/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 6/22/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 7/11/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 7/21/2023 | SINA KHOSRAVI |
| Plan Check Approved | 7/27/2023 | SINA KHOSRAVI |
| Issued | 8/9/2023 | APPLICANT |
| CofO in Progress | 11/13/2024 | WILLIAM SIERRA |
| Permit Finaled | 11/13/2024 | DEROLD HAUFF |
| CofO Issued | 11/13/2024 | DEROLD HAUFF |
| Permit Finaled | 11/13/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/11/2023 | YINGSHI HUANG |
| ZA Case | Cleared | 4/11/2023 | YINGSHI HUANG |
| ZI | Cleared | 4/11/2023 | YINGSHI HUANG |
| ZI | Cleared | 4/11/2023 | YINGSHI HUANG |
| Tenant Habitability Plan | Cleared | 4/19/2023 | ISMAEL HERNANDEZ |
| Address approval | Cleared | 4/29/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 5/2/2023 | STEVE MELGAR |
| Low Impact Development (LID) | Cleared | 6/14/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/25/2023 | AHMED AMARRAGY |
| Historic monument | Cleared | 6/28/2023 | DANIEL MATA |
| Specific Plan | Cleared | 6/28/2023 | DANIEL MATA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yiu,, Siu; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/12/2023 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 10/12/2023 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 10/12/2023 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 10/12/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 10/19/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Sewer | 10/19/2023 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 10/19/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 10/23/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 12/13/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/13/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/21/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 12/21/2023 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/21/2023 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 1/2/2024 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 1/3/2024 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 1/3/2024 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 1/12/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/27/2024 | Approved | JOSEPH MCGARRY |
| Final | 6/27/2024 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Final | 6/27/2024 | Approved | JOSEPH MCGARRY |
| METHANE-Rough | 6/27/2024 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 6/27/2024 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 6/27/2024 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 6/27/2024 | Approved | JOSEPH MCGARRY |
| Final | 7/19/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Gas Test | 7/26/2024 | Partial Approval | WILLIAM SIERRA |
| Final | 8/15/2024 | No Access for Inspection | WILLIAM SIERRA |
| Gas Test | 8/15/2024 | Approved | WILLIAM SIERRA |
| HVAC-Final | 8/15/2024 | No Access for Inspection | WILLIAM SIERRA |
| PLUMBING-Final | 8/15/2024 | No Access for Inspection | WILLIAM SIERRA |
| Final | 10/22/2024 | Corrections Issued | WILLIAM SIERRA |
| Final | 10/29/2024 | OK to Issue CofO | WILLIAM SIERRA |