4618 N NORWICH AVE 91403

Certificate Information: 4618 N NORWICH AVE 91403

Application / Permit
23010-10000-01269
Plan Check / Job No.
B23LA05463
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE TWO STORY ACCESSORY DWELLING UNIT (PER LAMC 12.22 A.33(c) and (d)) WITH ATTACHED STORAGE AND COVERED PATIO AT FIRST FLOOR.
Permit Issued
Issued on 1/22/2024
Issuing Office
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 DAWN MC NULTY
Corrections Issued 4/18/2023 DAWN MC NULTY
Quality Review Completed 4/19/2023 STEVEN KIM
Applicant returned to address corrections 11/7/2023 DAWN MC NULTY
Plan Check Approved 12/19/2023 DAWN MC NULTY
Issued 1/22/2024 APPLICANT
CofO in Progress 4/8/2025 JACK KARGODORIAN
CofO Issued 5/2/2025 RUBEN SALAS
Permit Finaled 5/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/1/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/4/2023 MEGAN GODINEZ
Sewer availability Cleared 5/22/2023 MEGAN GODINEZ
Hydrant and Access approval Cleared 7/6/2023 LAVEON RIDER
Construction near power lines Cleared 7/28/2023 TINA MIRANDA
Construction within easement Cleared 7/28/2023 TINA MIRANDA
Low Impact Development (LID) Cleared 11/6/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/15/2023 NIKKI ZULUETA

Contact Information

Contractor N A Design Builders; Lic. No.: 996566-B       ,
Contractor N A Designs Inc; Lic. No.: 996566-B       ,
Engineer Peek,, Justen N; Lic. No.: C76751 702 RIO GRANDE CT      BRENTWOOD, CA 94513

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/2/2024 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 4/2/2024 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 4/2/2024 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 4/4/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 7/8/2024 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 7/8/2024 Approved VINCENT HANLEY
HVAC-Rough 7/8/2024 Approved VINCENT HANLEY
PLUMBING-Rough 7/8/2024 Approved VINCENT HANLEY
Sewer 7/8/2024 Approved VINCENT HANLEY
Underground Mechanical 7/8/2024 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 7/8/2024 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 7/15/2024 Approved JACK KARGODORIAN
Shower Pan 7/15/2024 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 7/15/2024 Approved JACK KARGODORIAN
Shower Pan 7/18/2024 Approved JACK KARGODORIAN
Shower Pan 7/23/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 7/25/2024 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 8/15/2024 Partial Approval JACK KARGODORIAN
Insulation 9/13/2024 Approved JACK KARGODORIAN
Drywall Nailing 9/23/2024 Approved WILLIAM WREN
ELECTRICAL-Final 2/7/2025 Not Ready for Inspection JACK KARGODORIAN
Final 2/7/2025 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 2/7/2025 Approved JACK KARGODORIAN
HVAC-Final 2/7/2025 Approved JACK KARGODORIAN
PLUMBING-Final 2/7/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 2/7/2025 SGSOV Approved JACK KARGODORIAN
Service/Power Release 2/7/2025 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 2/7/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 3/26/2025 Not Ready for Inspection JACK KARGODORIAN
Final 3/26/2025 Corrections Issued JACK KARGODORIAN
Service/Power Release 3/26/2025 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Final 4/8/2025 Approved JACK KARGODORIAN
Final 4/8/2025 OK to Issue CofO JACK KARGODORIAN
Grounding or Bonding 4/8/2025 Approved JACK KARGODORIAN
Service/Power Release 4/8/2025 Approved JACK KARGODORIAN