10027 S HARVARD BLVD 90047
Certificate Information: 10027 S HARVARD BLVD 90047
- Application / Permit
- 23010-10000-01233
- Plan Check / Job No.
- B23LA05330
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **EPLAN** NEW 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) . Work per engineered design .
- Permit Issued
- Issued on 9/1/2023
- Issuing Office
- Current Status
- CofO Issued on 4/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2023 | GEORGE ALVAREZ |
| Corrections Issued | 4/13/2023 | GEORGE ALVAREZ |
| Plan Check Approved | 8/29/2023 | GEORGE ALVAREZ |
| Issued | 9/1/2023 | APPLICANT |
| CofO in Progress | 11/25/2024 | JOSE MACIAS |
| CofO in Progress | 11/25/2024 | JOSE MACIAS |
| Permit Finaled | 4/18/2025 | DEROLD HAUFF |
| CofO Issued | 4/18/2025 | DEROLD HAUFF |
| Permit Finaled | 4/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2023 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 5/26/2023 | HUGO LOPEZ |
| Low Impact Development (LID) | Cleared | 7/27/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/4/2023 | HUGO LOPEZ |
| Miscellaneous | Cleared | 8/29/2023 | GEORGE ALVAREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/29/2023 | No Access for Inspection | ENRIQUE MIRELES |
| METHANE-Barrier | 12/29/2023 | No Access for Inspection | ENRIQUE MIRELES |
| METHANE-Subgrade | 12/29/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 1/10/2024 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 1/10/2024 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 1/10/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 2/12/2024 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 2/12/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 2/12/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 2/12/2024 | Not Ready for Inspection | JOSE MACIAS |
| Verify Sprinkler Sign Off | 2/12/2024 | Not Ready for Inspection | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 3/4/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 4/10/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 4/10/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 4/10/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 4/18/2024 | Partial Approval | JOSE MACIAS |
| ELECTRICAL-Rough | 4/18/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 4/18/2024 | Corrections Issued | JOSE MACIAS |
| METHANE-Rough | 4/18/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 4/18/2024 | Approved | JOSE MACIAS |
| Verify Sprinkler Sign Off | 4/18/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 5/1/2024 | Approved | MICHAEL LEWIS |
| Insulation | 5/8/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 5/21/2024 | Approved | JOSE MACIAS |
| Shower Pan | 5/21/2024 | Not Ready for Inspection | JOSE MACIAS |
| Interior/Exterior Lathing | 6/6/2024 | Corrections Issued | JOSE MACIAS |
| Shower Pan | 6/6/2024 | Corrections Issued | JOSE MACIAS |
| Underground Mechanical | 6/6/2024 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 7/3/2024 | Approved | JOSE MACIAS |
| Sewer | 7/3/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 7/3/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 11/21/2024 | Approved | JOSE MACIAS |
| Final | 11/21/2024 | Conditional Approval | JOSE MACIAS |
| Green Building Final | 11/21/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 11/21/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 11/21/2024 | Approved | JOSE MACIAS |
| Smoke Detectors | 11/21/2024 | Approved | JOSE MACIAS |