1334 N WILMINGTON BLVD 90744

Certificate Information: 1334 N WILMINGTON BLVD 90744

Application / Permit
23010-10000-01227
Plan Check / Job No.
B23LA05309
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: (N) 2-Story ADU attached to (E) Garage
Permit Issued
Issued on 8/28/2023
Issuing Office
Current Status
CofO Issued on 3/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 SAM CHANG
Corrections Issued 4/25/2023 SAM CHANG
Quality Review Completed 4/27/2023 EUGENE BARBEAU
Applicant returned to address corrections 8/22/2023 SAM CHANG
Plan Check Approved 8/24/2023 SAM CHANG
Issued 8/28/2023 APPLICANT
CofO in Progress 3/22/2024 EUGENE CASSIDY
Permit Finaled 3/28/2024 ANSON MAGLASANG
Permit Finaled 3/28/2024 ANSON MAGLASANG
CofO Issued 3/28/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 5/8/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/22/2023 JEANIE LAM
Sewer availability Cleared 5/22/2023 JEANIE LAM
"Q" conditions Cleared 5/26/2023 MAXFIELD VERMY
Clean Up Green Up Cleared 5/26/2023 MAXFIELD VERMY
Hydrant and Access approval Cleared 6/13/2023 JOHN CONNEALLY
Low Impact Development (LID) Cleared 7/27/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 7/28/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/25/2023 Approved EUGENE CASSIDY
METHANE-Barrier 9/25/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 9/25/2023 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Partial Approval JAMES CHAVEZ
PLUMBING-Rough 10/6/2023 Partial Approval JAMES CHAVEZ
Wood Frame 10/13/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 10/31/2023 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 Partial Approval EUGENE CASSIDY
HVAC-Rough 10/31/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 10/31/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/8/2023 Approved EUGENE CASSIDY
Green Building Rough 11/8/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/8/2023 Partial Approval EUGENE CASSIDY
METHANE-Rough 11/8/2023 Approved EUGENE CASSIDY
Insulation 11/15/2023 Approved JAMES CHAVEZ
Drywall Nailing 11/27/2023 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 11/27/2023 Approved EUGENE CASSIDY
Drywall Nailing 12/5/2023 Corrections Issued EUGENE CASSIDY
Drywall Nailing 12/14/2023 Approved EUGENE CASSIDY
Sewer 12/14/2023 Approved EUGENE CASSIDY
Underground Mechanical 12/14/2023 Approved EUGENE CASSIDY
Final 3/1/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 3/1/2024 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 3/1/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 3/21/2024 Approved EUGENE CASSIDY
Final 3/21/2024 OK to Issue CofO EUGENE CASSIDY
Green Building Final 3/21/2024 Approved EUGENE CASSIDY
HVAC-Final 3/21/2024 Approved EUGENE CASSIDY
PLUMBING-Final 3/21/2024 Approved EUGENE CASSIDY
Smoke Detectors 3/21/2024 Approved EUGENE CASSIDY