7625 S DENKER AVE 90047
Certificate Information: 7625 S DENKER AVE 90047
- Application / Permit
- 23010-10000-01220
- Plan Check / Job No.
- B23LA05279
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30'-0" X 41'-8" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER ENGINEER
- Permit Issued
- Issued on 9/18/2023
- Issuing Office
- Current Status
- CofO Issued on 7/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 4/1/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 9/2/2023 | DANIEL ABRAMYAN |
| Issued | 9/18/2023 | APPLICANT |
| CofO in Progress | 7/20/2024 | JOSE MACIAS |
| Permit Finaled | 7/24/2024 | DEROLD HAUFF |
| CofO Issued | 7/24/2024 | DEROLD HAUFF |
| Permit Finaled | 7/24/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2023 | CHRISTOPHER ROCHA |
| Low Impact Development (LID) | Cleared | 7/27/2023 | ROGELIO CORTES |
| Construction near power lines | Cleared | 8/1/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/1/2023 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 8/6/2023 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 8/10/2023 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/4/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/11/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 10/25/2023 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 10/25/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/8/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 11/8/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/8/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 11/8/2023 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/14/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 11/14/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/14/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 11/14/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/20/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 11/30/2023 | Corrections Issued | ENRIQUE MIRELES |
| Sewer | 12/4/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/24/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 1/24/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 1/24/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 1/24/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 1/24/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 1/24/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Not Required | ALIZAH MAYAGOITIA |
| Service/Power Release | 1/24/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 1/24/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 1/26/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Final | 4/26/2024 | Corrections Issued | JOSE MACIAS |
| Service/Power Release | 4/26/2024 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Final | 5/29/2024 | Approved | JOSE MACIAS |
| Service/Power Release | 5/29/2024 | Approved | JOSE MACIAS |
| Final | 6/10/2024 | Corrections Issued | JOSE MACIAS |
| Final | 7/22/2024 | OK to Issue CofO | JOSE MACIAS |