1947 1/2 E 114TH ST 90059
Certificate Information: 1947 1/2 E 114TH ST 90059
- Application / Permit
- 23010-10000-01208
- Plan Check / Job No.
- B23LA05225
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1-STORY SFD PER SB 9 TWO-UNIT DEVELOPMENT CA 65852.21 ALL CONSTRUCTION PER WFPP. SOLAR INSTALLATION PER TITLE 24 REQ'D PRIOR TO C OF O
- Permit Issued
- Issued on 8/3/2023
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | VIVIAN LAO |
| Corrections Issued | 3/29/2023 | VIVIAN LAO |
| Quality Review Completed | 3/29/2023 | KEN GILL |
| Building Plans Picked Up | 4/7/2023 | APPLICANT |
| Quality Review Completed | 5/26/2023 | JOHN FRANCIA |
| Plan Check Approved | 7/14/2023 | VIVIAN LAO |
| Issued | 8/3/2023 | APPLICANT |
| CofO in Progress | 5/14/2024 | BEN MOLSTAD |
| Permit Finaled | 11/12/2024 | ANSON MAGLASANG |
| CofO Issued | 11/12/2024 | ANSON MAGLASANG |
| Permit Finaled | 11/12/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Senate Bill 9 | Cleared | 4/11/2023 | CLAUDE GOODING |
| Address approval | Cleared | 4/20/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 5/4/2023 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 5/26/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 6/22/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/28/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | De La Rosa Construction; Lic. No.: 855010-B | 3627 E FIRST STREET LOS ANGELES, CA 90063 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/4/2023 | Partial Approval | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 8/7/2023 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 8/7/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Partial Approval | JOHN KLARIN |
| HVAC-Rough | 9/6/2023 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 9/6/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 9/7/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 9/7/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 9/7/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 9/7/2023 | Approved | JOHN KLARIN |
| Insulation | 9/11/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 9/21/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 9/21/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 10/4/2023 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Final | 11/6/2023 | Not Ready for Inspection | JOHN KLARIN |
| Underground Mechanical | 11/27/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 2/16/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 2/21/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 2/22/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 3/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 3/5/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 3/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 3/5/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 3/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 3/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 3/19/2024 | Conditional Approval | BEN MOLSTAD |
| ELECTRICAL-Final | 4/15/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 4/15/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 4/15/2024 | No Access for Inspection | BEN MOLSTAD |
| HVAC-Final | 4/15/2024 | No Access for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 4/15/2024 | No Access for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 4/15/2024 | No Access for Inspection | BEN MOLSTAD |
| Smoke Detectors | 4/15/2024 | No Access for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 4/19/2024 | Conditional Approval | JAMES CHAVEZ |
| Final | 4/19/2024 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 4/19/2024 | Approved | JAMES CHAVEZ |
| HVAC-Final | 4/19/2024 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 4/19/2024 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 4/19/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 4/19/2024 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 5/13/2024 | Approved | BEN MOLSTAD |
| Final | 5/13/2024 | OK to Issue CofO | BEN MOLSTAD |
| Service/Power Release | 5/13/2024 | Approved | BEN MOLSTAD |