3255 1/2 W ROWENA AVE 90027
Certificate Information: 3255 1/2 W ROWENA AVE 90027
- Application / Permit
- 23010-10000-01204
- Plan Check / Job No.
- B23LA05220
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 20'-3" X 20'-3" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) - PER ENGINEER
- Permit Issued
- Issued on 12/11/2023
- Issuing Office
- Current Status
- CofO Issued on 1/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 4/1/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 5/10/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 5/17/2023 | DANIEL ABRAMYAN |
| No Progress | 12/11/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 12/11/2023 | DANIEL ABRAMYAN |
| Issued | 12/11/2023 | APPLICANT |
| CofO in Progress | 1/23/2025 | ENRIQUE MIRELES |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
| CofO Issued | 1/26/2025 | DEROLD HAUFF |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2023 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 5/3/2023 | ROBERT HUGHES |
| Sewer availability | Cleared | 5/12/2023 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 18759 WILLOWTREE LANE PORTER RANCH, CA 91326 |
| Engineer | Kim,, Hosang; Lic. No.: NA67288 | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/15/2023 | No Access for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/18/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 1/12/2024 | Corrections Issued | RICHARD DOCKUS |
| Underground Mechanical | 2/1/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 2/7/2024 | Approved | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 2/9/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Deputy Drilled-In Anchors | 2/16/2024 | Conditional Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 3/5/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 3/11/2024 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 3/22/2024 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 3/29/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 4/17/2024 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Rough | 4/17/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 4/23/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 4/23/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 5/6/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 5/6/2024 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/13/2024 | Corrections Issued | ENRIQUE MIRELES |
| Wood Frame | 5/24/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 5/29/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 6/21/2024 | Partial Approval | ENRIQUE MIRELES |
| Wood Frame | 6/21/2024 | Partial Approval | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 6/26/2024 | Approved | ENRIQUE MIRELES |
| Wood Frame | 6/26/2024 | Partial Approval | ENRIQUE MIRELES |
| Insulation | 6/28/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/8/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 7/8/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/18/2024 | No Access for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/24/2024 | Approved | JOSH MEISTER |
| Underground Mechanical | 10/8/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/21/2024 | Approved | ENRIQUE MIRELES |
| Final | 10/21/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 10/21/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/21/2024 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 12/9/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/11/2024 | No Access for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 12/11/2024 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 12/11/2024 | No Access for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 12/11/2024 | No Access for Inspection | ENRIQUE MIRELES |
| Final | 1/14/2025 | No Access for Inspection | JOAQUIN GREENOUGH |
| Final | 1/22/2025 | OK to Issue CofO | ENRIQUE MIRELES |