527 N SLOAT ST 90063
Certificate Information: 527 N SLOAT ST 90063
- Application / Permit
- 23010-10000-01199
- Plan Check / Job No.
- B23LA05216
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1,008 SQ FT 2 STORY SFD WITH ATTACHED CARPORT(44'X18'). ALL (NO GPI REPORT)
- Permit Issued
- Issued on 7/30/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | NGHI SU |
| Corrections Issued | 3/28/2023 | NGHI SU |
| Quality Review Completed | 3/30/2023 | KEN GILL |
| Building Plans Picked Up | 4/11/2023 | APPLICANT |
| Applicant returned to address corrections | 7/17/2024 | NGHI SU |
| Plan Check Approved | 7/29/2024 | NGHI SU |
| Issued | 7/30/2024 | APPLICANT |
| CofO in Progress | 8/21/2025 | ALIZAH MAYAGOITIA |
| CofO in Progress | 8/21/2025 | CHARLES BOGHOSKHAN |
| Permit Finaled | 8/23/2025 | DEROLD HAUFF |
| Permit Finaled | 8/23/2025 | DEROLD HAUFF |
| CofO Issued | 8/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2023 | TREVOR QUAN |
| Clean Up Green Up | Cleared | 5/9/2023 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 5/9/2023 | ASHLEY RODARTE |
| Grading Pre-Inspection | Cleared | 10/12/2023 | RUSSELL BONVOULOIR |
| Miscellaneous | Cleared | 4/10/2024 | SPENCER WEJROWSKI |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 4/11/2024 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 5/4/2024 | KURT CORRAL |
| ZI | Cleared | 6/4/2024 | DALIA MOKAYED |
| Low Impact Development (LID) | Cleared | 6/28/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/8/2024 | DAVID LOPEZ |
| GPI Written Notices | Cleared | 7/29/2024 | NGHI SU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/17/2024 | Corrections Issued | OSVALDO PARAMO |
| Special/Order Compliance | 9/17/2024 | Partial Inspection | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 9/26/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/3/2024 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/22/2024 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/22/2024 | Approved | OSVALDO PARAMO |
| METHANE-Barrier | 10/22/2024 | Approved | OSVALDO PARAMO |
| METHANE-Subgrade | 10/22/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 11/5/2024 | Partial Approval | LUIS CASTRO |
| Wood Frame | 11/5/2024 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 11/6/2024 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 11/6/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Partial Approval | LUIS CASTRO |
| Insulation | 11/8/2024 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 11/18/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/18/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 11/18/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 11/18/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 12/9/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 12/9/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/9/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 12/10/2024 | Corrections Issued | OSVALDO PARAMO |
| Interior/Exterior Lathing | 12/10/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 12/10/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/11/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 12/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Drywall Nailing | 1/14/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 1/14/2025 | Approved | JOHN QUINTANILLA |
| Shower Pan | 1/14/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 1/22/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 1/22/2025 | Corrections Issued | ANTHONY RAMOS |
| Shower Pan | 1/28/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Shower Pan | 2/3/2025 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 2/11/2025 | Approved | ANTHONY RAMOS |
| Sewer | 2/11/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 2/11/2025 | Partial Approval | ANTHONY RAMOS |
| Service/Power Release | 4/3/2025 | No Access for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/8/2025 | Corrections Issued | OSVALDO PARAMO |
| Service/Power Release | 4/8/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Underground Mechanical | 4/28/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 5/30/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/17/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 7/16/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 7/16/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 7/23/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 7/23/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 7/23/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 7/23/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/13/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 8/13/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Final | 8/13/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Rough | 8/13/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 8/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/21/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |