11931 W CURRITUCK DR 90049

Certificate Information: 11931 W CURRITUCK DR 90049

Application / Permit
23010-10000-01169
Plan Check / Job No.
B23LA05104
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Proposed two story single family dwelling with basement and a attached three-car garage. 1 of 3
Permit Issued
Issued on 5/2/2024
Issuing Office
Current Status
Issued on 5/2/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/22/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 CARLOS MONTES
Corrections Issued 4/25/2023 MICHAEL LOPEZ
Quality Review Completed 5/1/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 12/22/2023 MICHAEL LOPEZ
Applicant returned to address corrections 2/23/2024 MICHAEL LOPEZ
Applicant returned to address corrections 4/3/2024 MICHAEL LOPEZ
Plan Check Approved 5/2/2024 CARLOS MONTES
Issued 5/2/2024 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 5/24/2023 EDUARDO HERMOSO
Address approval Cleared 6/12/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 6/12/2023 JASON NG
Permit Cleared 6/12/2023 JASON NG
Sewer availability Cleared 6/12/2023 JASON NG
Hydrant and Access approval Cleared 8/8/2023 ERIC FRENCH
Trees in Parkway Cleared 9/9/2023 ADALBERTO VERA
Work Adjacent to Public Way Cleared 11/9/2023 HISASHI KOBAYAKAWA
Low Impact Development (LID) Cleared 2/9/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 2/15/2024 LIAM ODONOVAN
GPI Written Notices Cleared 2/23/2024 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 2/23/2024 CHARLES POWELL
Grading Pre-Inspection Cleared 2/23/2024 ROBERT PINA
Haul Route Cleared 2/23/2024 MICHAEL LOPEZ
Excavation more than 5-ft deep Cleared 4/3/2024 CALOSHA APPROVED
GPI Written Notices Cleared 4/3/2024 MICHAEL LOPEZ

Contact Information

Contractor Pillar Building Group Llc; Lic. No.: 1017041-B       ,
Engineer Daugherty,, Daniel Thomas; Lic. No.: C76588 31129 VIA COLINAS STE 707      WESTLAKE VILLAGE, CA 91362
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Moon,, Samuel; Lic. No.: NA49445       ,
Engineer Uhles,, Scott; Lic. No.: C72391 2812 SANTA MONICA BLVD, 206      SANTA MONICA, CA 90404
Geologist Daugherty,, Daniel Thomas; Lic. No.: EG2569 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/14/2024 Partial Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 6/18/2024 Approved ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 6/18/2024 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 8/5/2024 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 8/5/2024 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 8/5/2024 Partial Approval STEPHANIE SWANSON
Structural Steel Frame 8/5/2024 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 8/27/2024 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/6/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 9/6/2024 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 9/6/2024 Partial Inspection MICHAEL ALLEN
Deputy Steel/Welding 9/17/2024 Conditional Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 9/18/2024 Conditional Approval JESUS RODRIGUEZ
Deputy Steel/Welding 9/18/2024 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/18/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 9/18/2024 Partial Approval JESUS RODRIGUEZ
Deputy Steel/Welding 9/19/2024 Conditional Approval JESUS RODRIGUEZ
Deputy Steel/Welding 9/20/2024 Conditional Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 9/23/2024 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/4/2024 Partial Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 10/10/2024 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/15/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 11/14/2024 Partial Approval JESUS RODRIGUEZ
Deputy Steel/Welding 11/15/2024 Conditional Approval JESUS RODRIGUEZ
Deputy Steel/Welding 11/18/2024 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/7/2025 Partial Approval JESUS RODRIGUEZ
Deputy Steel/Welding 4/1/2025 Conditional Approval HERBERT GIRON
Deputy Steel/Welding 4/18/2025 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 Partial Approval HERBERT GIRON
Deputy Steel/Welding 4/22/2025 Conditional Approval HERBERT GIRON
Deputy Steel/Welding 4/24/2025 Conditional Approval HERBERT GIRON
Structural Steel Frame 4/29/2025 Partial Approval HERBERT GIRON
Deputy Reinf. Concrete 5/7/2025 No Access for Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 5/7/2025 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 5/21/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 6/18/2025 Partial Approval HERBERT GIRON
PLUMBING-Rough 7/1/2025 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 7/16/2025 Partial Approval HAMIK HARTOUNIAN
Deputy Steel/Welding 8/4/2025 Conditional Approval HERBERT GIRON
Deputy Steel/Welding 8/6/2025 Conditional Approval HERBERT GIRON
Deputy Steel/Welding 8/7/2025 Conditional Approval HERBERT GIRON
Structural Steel Frame 8/11/2025 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 8/25/2025 Corrections Issued HERBERT GIRON
Deputy Steel/Welding 9/11/2025 Conditional Approval HERBERT GIRON
Deputy Steel/Welding 9/12/2025 Conditional Approval HERBERT GIRON
Deputy Wood Construction 10/3/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 10/3/2025 Approved HERBERT GIRON
Structural Steel Frame 10/3/2025 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Partial Approval HERBERT GIRON
HVAC-Rough 12/23/2025 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 1/16/2026 Corrections Issued HERBERT GIRON
HVAC-Rough 1/23/2026 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 1/23/2026 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 1/26/2026 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 2/12/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 2/13/2026 Conditional Approval HERBERT GIRON
Green Building Rough 2/13/2026 Approved HERBERT GIRON
HVAC-Rough 2/13/2026 Conditional Approval HERBERT GIRON
PLUMBING-Rough 2/13/2026 Approved HERBERT GIRON
BUILDING-Rough-Frame 2/25/2026 Approved HERBERT GIRON
Final 2/25/2026 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/25/2026 Approved HERBERT GIRON
Structural Steel Frame 2/25/2026 Approved HERBERT GIRON
Verify Sprinkler Sign Off 2/25/2026 Approved HERBERT GIRON
Insulation 4/1/2026 Partial Approval HERBERT GIRON
Insulation 4/16/2026 Approved KEVIN SARGSYAN
Drywall Nailing 5/5/2026 Approved KEVIN SARGSYAN
Shower Pan 5/18/2026 Approved HERBERT GIRON
Interior/Exterior Lathing 6/1/2026 Approved HERBERT GIRON
Sewer 6/17/2026 Partial Approval HERBERT GIRON