419 E 97TH ST 90003
Certificate Information: 419 E 97TH ST 90003
- Application / Permit
- 23010-10000-01164
- Plan Check / Job No.
- B23LA05090
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1-STORY FAMILY DWELLING (AT FRONT OF LOT) W/ATTACHED TWO CAR GARAGE PER WFPP
- Permit Issued
- Issued on 7/18/2023
- Issuing Office
- Current Status
- CofO Issued on 2/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | ADRIANA LOPEZ |
| Corrections Issued | 4/10/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 4/19/2023 | KEN GILL |
| Building Plans Picked Up | 5/1/2023 | APPLICANT |
| Plan Check Approved | 7/17/2023 | ADRIANA LOPEZ |
| Issued | 7/18/2023 | APPLICANT |
| CofO in Progress | 2/16/2024 | BEN MOLSTAD |
| CofO in Progress | 2/16/2024 | BEN MOLSTAD |
| CofO in Progress | 2/22/2024 | ANSON MAGLASANG |
| Permit Finaled | 2/22/2024 | ANSON MAGLASANG |
| CofO Issued | 2/22/2024 | ANSON MAGLASANG |
| Permit Finaled | 2/22/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2023 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/10/2023 | ADRIAN SANCHEZ |
| Low Impact Development (LID) | Cleared | 6/8/2023 | ANTHONY VARGAS |
| Hydrant and Access approval | Cleared | 7/3/2023 | GILBERT URREA |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 7/17/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/31/2023 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 8/31/2023 | Approved | JOHN KLARIN |
| Grounding or Bonding | 8/31/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 8/31/2023 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 9/7/2023 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 9/7/2023 | Not Ready for Inspection | JOHN KLARIN |
| Underground Mechanical | 9/7/2023 | Partial Approval | JOHN KLARIN |
| Verify Sprinkler Sign Off | 9/7/2023 | Not Ready for Inspection | JOHN KLARIN |
| Insulation | 9/8/2023 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 9/22/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 9/22/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2023 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 9/22/2023 | Not Ready for Inspection | JOHN KLARIN |
| HVAC-Rough | 9/22/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 9/22/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 9/22/2023 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/4/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 10/4/2023 | Approved | JOHN KLARIN |
| HVAC-Rough | 10/4/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 10/4/2023 | Approved | JOHN KLARIN |
| Insulation | 10/16/2023 | Approved | ROBERT CORNELL |
| Drywall Nailing | 10/17/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 10/17/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 12/27/2023 | No Access for Inspection | JOHN KLARIN |
| Final | 12/27/2023 | No Access for Inspection | JOHN KLARIN |
| Gas Test | 12/27/2023 | No Access for Inspection | JOHN KLARIN |
| Green Building Final | 12/27/2023 | No Access for Inspection | JOHN KLARIN |
| HVAC-Final | 12/27/2023 | No Access for Inspection | JOHN KLARIN |
| PLUMBING-Final | 12/27/2023 | No Access for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/27/2023 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 12/27/2023 | No Access for Inspection | JOHN KLARIN |
| Smoke Detectors | 12/27/2023 | No Access for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 12/28/2023 | No Access for Inspection | JOHN KLARIN |
| Gas Test | 12/28/2023 | No Access for Inspection | JOHN KLARIN |
| HVAC-Final | 12/28/2023 | No Access for Inspection | JOHN KLARIN |
| PLUMBING-Final | 12/28/2023 | No Access for Inspection | JOHN KLARIN |
| Service/Power Release | 12/28/2023 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 1/11/2024 | Corrections Issued | JOHN KLARIN |
| Final | 1/11/2024 | Corrections Issued | JOHN KLARIN |
| Gas Test | 1/11/2024 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 1/11/2024 | Approved | JOHN KLARIN |
| HVAC-Final | 1/11/2024 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 1/11/2024 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 1/11/2024 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 1/11/2024 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 1/11/2024 | Approved | JOHN KLARIN |
| Final | 1/23/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Not Ready | JAMES CHAVEZ |
| Service/Power Release | 1/23/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 2/1/2024 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 2/1/2024 | Not Ready for Inspection | JOHN KLARIN |
| Final | 2/13/2024 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Approved | BEN MOLSTAD |
| Service/Power Release | 2/13/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 2/15/2024 | Approved | BEN MOLSTAD |
| Final | 2/15/2024 | OK to Issue CofO | BEN MOLSTAD |
| HVAC-Final | 2/15/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 2/15/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 2/15/2024 | Approved | BEN MOLSTAD |