3754 1/2 S HARVARD BLVD 90018

Certificate Information: 3754 1/2 S HARVARD BLVD 90018

Application / Permit
23010-10000-01160
Plan Check / Job No.
B23LA05059
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-STORY DUPLEX W/ATTACHED ADU 10,041 SF
Permit Issued
Issued on 11/29/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 ARSALAN SHABESTARI
Corrections Issued 3/28/2023 ARSALAN SHABESTARI
Quality Review Completed 3/30/2023 KEN GILL
Building Plans Picked Up 7/19/2023 APPLICANT
Disabled Access Plans Picked Up 7/19/2023 APPLICANT
Plan Check Approved 8/23/2023 ARSALAN SHABESTARI
Issued 11/29/2023 APPLICANT
CofO in Progress 4/17/2025 SABAS ALONSO
Permit Finaled 4/19/2025 DEROLD HAUFF
CofO Issued 4/19/2025 DEROLD HAUFF
Permit Finaled 4/19/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/30/2023 ADRIAN SANCHEZ
Highway dedication Cleared 4/30/2023 ADRIAN SANCHEZ
Permit Cleared 4/30/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 5/31/2023 ADRIAN SANCHEZ
Sewer availability Cleared 5/31/2023 ADRIAN SANCHEZ
Low Impact Development (LID) Cleared 7/6/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 7/6/2023 ADRIAN SANCHEZ
SB8 RUD Cleared 7/18/2023 MARY ARCENA
Hydrant and Access approval Cleared 7/21/2023 KURT CORRAL
DAS Clearance Cleared 8/22/2023 ARSALAN SHABESTARI
Green Code Cleared 8/23/2023 ARSALAN SHABESTARI

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/13/2024 Corrections Issued SABAS ALONSO
Excavation/Setback/Form/Re-Bar 3/6/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 3/6/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Partial Approval ANTHONY EGSON
Deputy Wood Construction 8/19/2024 Conditional Approval ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 No Access for Inspection SABAS ALONSO
Green Building Rough 11/14/2024 Approved SABAS ALONSO
Verify Sprinkler Sign Off 11/14/2024 Approved SABAS ALONSO
Wood Frame 11/14/2024 Approved SABAS ALONSO
Insulation 11/19/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 11/19/2024 Partial Approval SABAS ALONSO
Drywall Nailing 11/27/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 12/2/2024 Approved SABAS ALONSO
Final 4/3/2025 No Access for Inspection SABAS ALONSO
Green Building Final 4/3/2025 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 4/3/2025 No Access for Inspection SABAS ALONSO
Final 4/11/2025 Corrections Issued SABAS ALONSO
Green Building Final 4/11/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/11/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 4/11/2025 Approved SABAS ALONSO
Final 4/16/2025 OK to Issue CofO SABAS ALONSO