1220 E APPLETON WAY 90291

Certificate Information: 1220 E APPLETON WAY 90291

Application / Permit
23010-10000-01134
Plan Check / Job No.
B23LA04945
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan New 2-story second dwelling per SB9. per SB9 Two-Unit Development Ca Govt Code 65852.21
Permit Issued
Issued on 8/7/2023
Issuing Office
Current Status
CofO Issued on 6/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 JAD BASMA
Corrections Issued 4/6/2023 JAD BASMA
Quality Review Completed 4/13/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 7/18/2023 JAD BASMA
Applicant returned to address corrections 8/2/2023 JAD BASMA
Plan Check Approved 8/3/2023 JAD BASMA
Issued 8/7/2023 APPLICANT
CofO in Progress 6/18/2025 JESUS RODRIGUEZ
Permit Finaled 6/26/2025 RICHARD STEINBACH
CofO Issued 6/26/2025 RICHARD STEINBACH
Permit Finaled 6/26/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/20/2023 DARIN LAM
Senate Bill 9 Cleared 4/26/2023 CLAUDE GOODING
Eng Process Fee Ord 176,300 Cleared 5/3/2023 DARIN LAM
Sewer availability Cleared 5/3/2023 DARIN LAM
Hydrant and Access approval Cleared 5/16/2023 MATTHEW CRAIG
Specific Plan Cleared 6/7/2023 PEDRO AYALA
Low Impact Development (LID) Cleared 6/14/2023 TOMMY YIN
GPI Written Notices Cleared 7/18/2023 JAD BASMA
Grading Pre-Inspection Cleared 7/18/2023 JAD BASMA
Roof/Waste drainage to street Cleared 7/25/2023 DARIN LAM

Contact Information

Architect Fallen,, Keith; Lic. No.: NA34528       ,
Contractor Clark Kitchen Cabinets; Lic. No.: 645164-B       ,
Engineer Perazzelli,, Joseph Ames; Lic. No.: NA35270       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/15/2023 Approved HERBERT GIRON
Underground Mechanical 8/15/2023 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 9/6/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 9/22/2023 Partial Approval HERBERT GIRON
PLUMBING-Rough 9/22/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Partial Approval HERBERT GIRON
Green Building Rough 10/23/2023 Not Ready for Inspection HERBERT GIRON
Verify Sprinkler Sign Off 10/23/2023 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Conditional Approval HERBERT GIRON
Deputy Wood Construction 11/29/2023 Conditional Approval HERBERT GIRON
PLUMBING-Rough 12/27/2023 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 4/1/2024 Approved HERBERT GIRON
HVAC-Rough 4/1/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 4/8/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Approved HERBERT GIRON
HVAC-Rough 4/8/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 4/8/2024 Partial Approval HERBERT GIRON
Special/Order Compliance 4/8/2024 Approved HERBERT GIRON
Verify Sprinkler Sign Off 4/8/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 4/15/2024 Approved HERBERT GIRON
Green Building Rough 4/15/2024 Approved HERBERT GIRON
Insulation 4/15/2024 Corrections Issued HERBERT GIRON
Drywall Nailing 4/25/2024 Approved HERBERT GIRON
Insulation 4/25/2024 Approved HERBERT GIRON
Shower Pan 7/15/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 7/17/2024 Partial Approval ARAM AVEDISIAN
HVAC-Final 2/12/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Final 2/12/2025 Not Ready for Inspection MICHAEL ALLEN
HVAC-Final 2/18/2025 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 2/18/2025 Approved HERBERT GIRON
ELECTRICAL-Final 2/20/2025 Approved JESUS PINEDA
Final 2/21/2025 Corrections Issued HERBERT GIRON
Green Building Final 2/21/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Not Required HERBERT GIRON
Smoke Detectors 2/21/2025 Approved HERBERT GIRON
Final 2/25/2025 Corrections Issued HERBERT GIRON
HVAC-Final 2/25/2025 Approved HERBERT GIRON
Final 6/16/2025 OK to Issue CofO JESUS RODRIGUEZ
Service/Power Release 6/16/2025 Approved JESUS RODRIGUEZ