4324 N GARDEN HOMES AVE 90032
Certificate Information: 4324 N GARDEN HOMES AVE 90032
- Application / Permit
- 23010-10000-01062
- Plan Check / Job No.
- B23LA04532
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD W/ ATTACHED GARAGE (51'4" x 29'9") @ FRONT OF LOT
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | NGHI SU |
| Corrections Issued | 3/18/2023 | NGHI SU |
| Quality Review Completed | 3/23/2023 | KEN GILL |
| Building Plans Picked Up | 4/20/2023 | APPLICANT |
| Applicant returned to address corrections | 6/5/2023 | NGHI SU |
| Plan Check Approved | 6/13/2023 | NGHI SU |
| Issued | 6/29/2023 | APPLICANT |
| CofO in Progress | 7/24/2024 | LILIANA PORTILLO |
| CofO in Progress | 7/31/2024 | LILIANA PORTILLO |
| CofO Issued | 8/5/2024 | DEROLD HAUFF |
| Permit Finaled | 8/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/21/2023 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 4/28/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 5/2/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 5/4/2023 | CELINA MORENO |
| Address approval | Cleared | 5/12/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2023 | CELINA MORENO |
| GPI Written Notices | Cleared | 6/5/2023 | NGHI SU |
| Grading Pre-Inspection | Cleared | 6/13/2023 | NGHI SU |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Montemayor,, G F; Lic. No.: C25258 | 1617 S WAVERLY GLEN WAY HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/3/2023 | Not Ready for Inspection | AMY COLIN |
| PLUMBING-Rough | 7/3/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 7/11/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 7/14/2023 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | AMY COLIN |
| Drywall Nailing | 9/28/2023 | Not Ready for Inspection | AMY COLIN |
| Green Building Rough | 9/28/2023 | Not Ready for Inspection | AMY COLIN |
| Wood Frame | 9/28/2023 | Not Ready for Inspection | AMY COLIN |
| Insulation | 9/29/2023 | Not Ready for Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 11/6/2023 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Rough | 11/6/2023 | Corrections Issued | AMY COLIN |
| Green Building Rough | 11/6/2023 | Approved | AMY COLIN |
| HVAC-Rough | 11/6/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 11/6/2023 | Approved | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 11/6/2023 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 11/6/2023 | Approved | AMY COLIN |
| Insulation | 11/28/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 11/28/2023 | Partial Approval | AMY COLIN |
| Drywall Nailing | 12/22/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 12/22/2023 | Approved | AMY COLIN |
| Shower Pan | 12/22/2023 | Approved | AMY COLIN |
| ELECTRICAL-Final | 5/24/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 5/24/2024 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 5/24/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 5/24/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/18/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 7/18/2024 | Approved | LILIANA PORTILLO |
| Final | 7/18/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 7/18/2024 | Approved | LILIANA PORTILLO |
| HVAC-Final | 7/18/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 7/18/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 7/18/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 7/18/2024 | Approved | LILIANA PORTILLO |
| Final | 7/23/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Final | 7/30/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 7/30/2024 | Approved | LILIANA PORTILLO |