12127-12131 W PALMS BLVD 90066

Certificate Information: 12127-12131 W PALMS BLVD 90066

Application / Permit
23010-10000-01061
Plan Check / Job No.
B23LA04520
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan NEW 2 STORY DUPLEX WITH ATT. ADU, ATTACHED GARAGE. USING SB9 TWO-UNIT DEVELOPMENT STANDARDS
Permit Issued
Issued on 8/16/2023
Issuing Office
Current Status
CofO Issued on 8/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 VU NGUYEN
Assigned to Zoning Architect 3/16/2023 CALEB WONG
Corrections Issued 3/28/2023 VU NGUYEN
Quality Review Completed 3/29/2023 EUGENE BARBEAU
Plan Check Approved 8/14/2023 VU NGUYEN
Issued 8/16/2023 APPLICANT
CofO in Progress 7/24/2025 KIRK SANDERS
Permit Finaled 8/12/2025 RICHARD STEINBACH
CofO Issued 8/12/2025 RICHARD STEINBACH
Permit Finaled 8/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

CPC Cleared 4/11/2023 RYAN LY
CPC Cleared 4/11/2023 RYAN LY
ZI Cleared 4/11/2023 RYAN LY
Senate Bill 9 Cleared 4/12/2023 RYAN LY
Disturb/Remove Protected Trees Cleared 5/3/2023 ADALBERTO VERA
Address approval Cleared 5/10/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/15/2023 DINAH GARIN
Hydrant and Access approval Cleared 6/6/2023 RUEL COLE
Low Impact Development (LID) Cleared 6/9/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 6/12/2023 DINAH GARIN
Zoning Plan Check Cleared 6/15/2023 CALEB WONG
Sewer availability Cleared 7/19/2023 DINAH GARIN
Specific Plan Cleared 8/5/2023 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,
Engineer Mahmoudkhani,, Behnam; Lic. No.: C88488 120 W WILSON AVE 1550      GLENDALE, CA 91203
Engineer Pirbadian,, Amir; Lic. No.: C72413 17514 VENTURA BLVD.   SUITE 206    ENCINO, CA 91346

Inspector Information

ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/23/2023 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 8/23/2023 Corrections Issued MICHAEL PELHAM
Pre-Inspection 8/23/2023 Partial Inspection MICHAEL PELHAM
Special/Order Compliance 8/23/2023 Partial Inspection BEN MOLSTAD
Special/Order Compliance 8/23/2023 Partial Inspection CLAYTON GRAHAM
Special/Order Compliance 8/23/2023 Partial Inspection TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 12/15/2023 Partial Approval JESUS PINEDA
Deputy Reinf. Concrete 12/18/2023 Conditional Approval JESUS PINEDA
PLUMBING-Rough 12/28/2023 Partial Approval JESUS PINEDA
Deputy Steel/Welding 1/5/2024 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 1/8/2024 Partial Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 1/9/2024 Partial Approval JESUS PINEDA
Deputy Reinf. Concrete 1/10/2024 Conditional Approval JESUS PINEDA
Deputy Steel/Welding 1/18/2024 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/22/2024 Partial Approval JESUS PINEDA
Deputy Steel/Welding 3/22/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 4/9/2024 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 4/25/2024 Corrections Issued JESUS PINEDA
Deputy Reinf. Concrete 5/2/2024 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 Partial Approval HERBERT GIRON
Deputy Shotcrete 5/20/2024 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 6/14/2024 Corrections Issued JESUS PINEDA
Underground Mechanical 7/19/2024 Approved JESUS PINEDA
Sewer 7/22/2024 Not Ready for Inspection TEMISTOCLES CAAL
Underground Mechanical 7/23/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 8/8/2024 Approved JESUS PINEDA
HVAC-Rough 8/22/2024 Corrections Issued JESUS PINEDA
Shower Pan 8/22/2024 Corrections Issued JESUS PINEDA
HVAC-Rough 8/27/2024 Corrections Issued DANIEL VERA
Shower Pan 8/30/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 9/3/2024 Conditional Approval DANIEL VERA
Drywall Nailing 9/3/2024 Corrections Issued DANIEL VERA
Green Building Rough 9/3/2024 Approved DANIEL VERA
Verify Sprinkler Sign Off 9/3/2024 Approved DANIEL VERA
Insulation 9/24/2024 Corrections Issued DANIEL VERA
Interior/Exterior Lathing 9/24/2024 Partial Approval DANIEL VERA
Insulation 9/30/2024 Approved MICHAEL ALLEN
Drywall Nailing 10/4/2024 Conditional Approval DANIEL VERA
Interior/Exterior Lathing 10/4/2024 Approved DANIEL VERA
ELECTRICAL-Final 6/10/2025 Approved WILBER ROSALES
Service/Power Release 6/10/2025 Approved WILBER ROSALES
PLUMBING-Final 6/13/2025 Corrections Issued WILBER ROSALES
BUILDING-Rough-Frame 7/14/2025 Approved WILBER ROSALES
Final 7/14/2025 Corrections Issued WILBER ROSALES
Footing/Foundation/Slab 7/14/2025 Approved WILBER ROSALES
Green Building Final 7/14/2025 Approved WILBER ROSALES
HVAC-Final 7/14/2025 Approved WILBER ROSALES
PLUMBING-Final 7/14/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 7/14/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 7/14/2025 Approved WILBER ROSALES
Final 7/18/2025 Corrections Issued WILBER ROSALES
Final 7/23/2025 OK to Issue CofO KIRK SANDERS