1919 S FEDERAL AVE 90025

Certificate Information: 1919 S FEDERAL AVE 90025

Application / Permit
23010-10000-01038
Plan Check / Job No.
B23LA03845
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE (MIDDLE)
Permit Issued
Issued on 3/18/2024
Issuing Office
Current Status
CofO Issued on 6/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2023 APPLICANT
Assigned to Plan Check Engineer 3/9/2023 KEVIN MORALES
Corrections Issued 3/13/2023 KEVIN MORALES
Quality Review Completed 3/14/2023 EUGENE BARBEAU
Applicant returned to address corrections 4/18/2023 KEVIN MORALES
Applicant returned to address corrections 6/20/2023 KEVIN MORALES
Applicant returned to address corrections 11/6/2023 KEVIN MORALES
Plan Check Approved 3/12/2024 KEVIN MORALES
Issued 3/18/2024 APPLICANT
CofO in Progress 6/5/2025 KIRK SANDERS
Permit Finaled 6/9/2025 RICHARD STEINBACH
CofO Issued 6/9/2025 RICHARD STEINBACH
Permit Finaled 6/9/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/21/2023 DINAH GARIN
Highway dedication Cleared 3/22/2023 AHMED AMARRAGY
Specific Plan Cleared 5/31/2023 ALESSANDRO MERCURI
Hydrant and Access approval Cleared 10/25/2023 LAVEON RIDER
Low Impact Development (LID) Cleared 10/27/2023 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 10/29/2023 AHMED AMARRAGY
Roof/Waste drainage to street Cleared 10/29/2023 AHMED AMARRAGY
Sewer availability Cleared 10/29/2023 AHMED AMARRAGY
SB8 RUD Cleared 10/30/2023 SAMANTHA RIVERA

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/21/2024 Corrections Issued KIRK SANDERS
Underground Mechanical 5/21/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 5/24/2024 Partial Approval KIRK SANDERS
Underground Mechanical 5/24/2024 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 6/6/2024 Partial Approval KIRK SANDERS
Deputy Reinf. Concrete 6/10/2024 Conditional Approval KIRK SANDERS
Footing/Foundation/Slab 6/18/2024 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 7/11/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Conditional Approval KIRK SANDERS
BUILDING-Rough-Frame 7/29/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Conditional Approval KIRK SANDERS
Wood Frame 8/28/2024 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 9/25/2024 Partial Approval CARLOS MATAMOROS
HVAC-Rough 10/22/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 10/23/2024 Approved KIRK SANDERS
Shower Pan 10/23/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 10/30/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 10/30/2024 Approved KIRK SANDERS
Green Building Rough 10/30/2024 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 10/30/2024 Approved KIRK SANDERS
Verify Sprinkler Sign Off 10/30/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 11/8/2024 Approved KIRK SANDERS
Green Building Rough 11/8/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 11/8/2024 Partial Approval KIRK SANDERS
Insulation 11/25/2024 Approved ARAM AVEDISIAN
Drywall Nailing 12/3/2024 Approved REGINA MENDEZ
Interior/Exterior Lathing 12/6/2024 Approved KIRK SANDERS
Sewer 2/24/2025 Approved REGINA MENDEZ
PLUMBING-Final 4/7/2025 Conditional Approval KIRK SANDERS
Special/Order Compliance 4/7/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 4/11/2025 Approved KIRK SANDERS
HVAC-Final 4/23/2025 Approved KIRK SANDERS
Deputy Other (see comments) 4/29/2025 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 4/29/2025 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 4/29/2025 Conditional Approval MICHAEL PELHAM
Service/Power Release 4/29/2025 Approved MICHAEL PELHAM
Final 5/5/2025 Conditional Approval KIRK SANDERS
Green Building Final 5/5/2025 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/5/2025 SGSOV Not Required KIRK SANDERS
Smoke Detectors 5/5/2025 Approved KIRK SANDERS
Final 6/5/2025 OK to Issue CofO KIRK SANDERS