15502-15504 W CHASE AVE 91343

Certificate Information: 15502-15504 W CHASE AVE 91343

Application / Permit
23010-10000-01010
Plan Check / Job No.
B23LA04213
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW THREE STORY DUPLEX WITH TUCK IN PARKING (CARPORT) AT FRONT OF LOT FIRE SPRINKLERED NFPA 13D THROUGH OUT
Permit Issued
Issued on 4/25/2024
Issuing Office
Metro
Current Status
CofO Issued on 8/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 JAD BASMA
Corrections Issued 3/18/2023 JAD BASMA
Quality Review Completed 3/24/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 4/14/2023 APPLICANT
Applicant returned to address corrections 6/1/2023 JAD BASMA
Plan Check Approved 4/25/2024 JAD BASMA
Issued 4/25/2024 APPLICANT
CofO in Progress 8/22/2025 DAVID MATSON
Permit Finaled 8/26/2025 RUBEN SALAS
CofO Issued 8/26/2025 RUBEN SALAS
Permit Finaled 8/26/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/24/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/25/2023 CARLOS AGUILERA
"T" removal Cleared 6/20/2023 JASON CHAN
Opn space landscape/Water mgmt Cleared 6/20/2023 JASON CHAN
Trees in Parkway Cleared 6/28/2023 ADALBERTO VERA
Low Impact Development (LID) Cleared 9/6/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 9/6/2023 CARLOS AGUILERA
Sewer availability Cleared 9/7/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/8/2023 KURT CORRAL
Permit Cleared 9/14/2023 CARLOS AGUILERA
Highway dedication Cleared 9/25/2023 CARLOS AGUILERA
SB8 RUD Cleared 4/24/2024 DORIS KWOK

Contact Information

Contractor Ganpat Properties; Lic. No.: 778755-B 2606 FOOTHILL BLVD SUITE #E      LA CRESCENTA, CA 91214

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/22/2024 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 5/31/2024 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 5/31/2024 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 5/31/2024 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 6/10/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 6/10/2024 Approved VINCENT HANLEY
Sewer 7/2/2024 Approved VINCENT HANLEY
Deputy Steel/Welding 7/12/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Partial Approval VINCENT HANLEY
Wood Frame 7/24/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Partial Approval VINCENT HANLEY
Green Building Rough 8/14/2024 Not Ready for Inspection VINCENT HANLEY
MERV13>=Rough 8/14/2024 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 8/14/2024 Not Ready for Inspection VINCENT HANLEY
Deputy Wood Construction 8/15/2024 Conditional Approval DAVID MATSON
Deputy Wood Construction 9/17/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Partial Approval VINCENT HANLEY
Green Building Rough 9/27/2024 Not Ready for Inspection VINCENT HANLEY
MERV13>=Rough 9/27/2024 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 9/27/2024 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 9/27/2024 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 11/7/2024 Corrections Issued VINCENT HANLEY
HVAC-Rough 11/15/2024 Approved VINCENT HANLEY
PLUMBING-Rough 11/15/2024 Approved VINCENT HANLEY
Shower Pan 11/15/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/20/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 11/20/2024 Approved VINCENT HANLEY
Green Building Rough 11/20/2024 Approved VINCENT HANLEY
MERV13>=Rough 11/20/2024 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 11/20/2024 Approved VINCENT HANLEY
Insulation 11/26/2024 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 11/26/2024 Approved VINCENT HANLEY
Insulation 12/3/2024 Approved VINCENT HANLEY
Drywall Nailing 12/11/2024 Approved LOUIS ESCOTO
Underground Mechanical 3/25/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 4/16/2025 Corrections Issued VINCENT HANLEY
HVAC-Final 4/16/2025 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 4/25/2025 Approved VINCENT HANLEY
HVAC-Final 4/25/2025 Approved VINCENT HANLEY
PLUMBING-Final 4/25/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/2/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 7/2/2025 Approved VINCENT HANLEY
Final 7/2/2025 Corrections Issued VINCENT HANLEY
Green Building Final 7/2/2025 Approved VINCENT HANLEY
HVAC-Final 7/2/2025 Approved VINCENT HANLEY
MERV13>=Final 7/2/2025 Approved VINCENT HANLEY
PLUMBING-Final 7/2/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Not Required VINCENT HANLEY
Service/Power Release 7/2/2025 Approved VINCENT HANLEY
Smoke Detectors 7/2/2025 Approved VINCENT HANLEY
Final 8/22/2025 OK to Issue CofO DAVID MATSON