5350 E OAKLAND ST 90032
Certificate Information: 5350 E OAKLAND ST 90032
- Application / Permit
- 23010-10000-00998
- Plan Check / Job No.
- B23LA04154
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: 3-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 1/18/2024
- Issuing Office
- Current Status
- CofO Issued on 2/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | DANIEL YIP |
| Corrections Issued | 3/18/2023 | DANIEL YIP |
| Quality Review Completed | 3/20/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/18/2023 | DANIEL YIP |
| Applicant returned to address corrections | 12/29/2023 | DANIEL YIP |
| Plan Check Approved | 1/10/2024 | DANIEL YIP |
| Issued | 1/18/2024 | APPLICANT |
| CofO in Progress | 2/12/2026 | LILIANA PORTILLO |
| Permit Finaled | 2/13/2026 | DEROLD HAUFF |
| CofO Issued | 2/13/2026 | DEROLD HAUFF |
| Permit Finaled | 2/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2023 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 6/6/2023 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 6/16/2023 | TREVOR QUAN |
| Frnt yard landscape/Water mgmt | Cleared | 6/21/2023 | MAYELA VILLA |
| Opn space landscape/Water mgmt | Cleared | 6/21/2023 | MAYELA VILLA |
| Low Impact Development (LID) | Cleared | 9/22/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/21/2023 | TREVOR QUAN |
| GPI Written Notices | Cleared | 1/10/2024 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 1/10/2024 | DANIEL YIP |
Contact Information
| Contractor | Bpc Development Inc; Lic. No.: 1059885-B | , |
| Contractor | Builder Point Construction; Lic. No.: 1059885-B | , |
| Engineer | Salto,, Alvaro; Lic. No.: NA83859 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/16/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 5/16/2024 | Conditional Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 6/13/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Approved | LILIANA PORTILLO |
| Special/Order Compliance | 10/16/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 10/21/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 10/28/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 10/28/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Rough | 10/30/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 10/30/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/19/2024 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/19/2024 | Conditional Approval | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 11/19/2024 | Approved | LILIANA PORTILLO |
| Insulation | 12/13/2024 | No Access for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/13/2024 | No Access for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/18/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 12/18/2024 | Approved | LILIANA PORTILLO |
| Insulation | 12/18/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/18/2024 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 12/31/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 2/21/2025 | Approved | LILIANA PORTILLO |
| Shower Pan | 2/21/2025 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 5/1/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/26/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 6/26/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 6/26/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 6/26/2025 | Corrections Issued | LILIANA PORTILLO |
| Verify Rec and Parks Fee Memo | 7/25/2025 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 10/17/2025 | Corrections Issued | LILIANA PORTILLO |
| Smoke Detectors | 10/17/2025 | Approved | LILIANA PORTILLO |
| HVAC-Final | 10/21/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 10/22/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/22/2025 | SGSOV Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/27/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/7/2025 | Corrections Issued | LILIANA PORTILLO |
| Final | 11/24/2025 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 11/24/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/8/2025 | Approved | LILIANA PORTILLO |
| HVAC-Final | 12/9/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| HVAC-Final | 12/11/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/13/2026 | Approved | LILIANA PORTILLO |
| Final | 1/13/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 1/13/2026 | Approved | LILIANA PORTILLO |
| Green Building Final | 1/13/2026 | Approved | LILIANA PORTILLO |
| Service/Power Release | 1/13/2026 | Approved | LILIANA PORTILLO |
| Final | 2/3/2026 | Conditional Approval | ALIZAH MAYAGOITIA |
| Service/Power Release | 2/3/2026 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/11/2026 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 2/11/2026 | Approved | LILIANA PORTILLO |