5350 E OAKLAND ST 90032

Certificate Information: 5350 E OAKLAND ST 90032

Application / Permit
23010-10000-00998
Plan Check / Job No.
B23LA04154
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: 3-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/18/2024
Issuing Office
Current Status
CofO Issued on 2/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 DANIEL YIP
Corrections Issued 3/18/2023 DANIEL YIP
Quality Review Completed 3/20/2023 GARO TELMI
Applicant returned to address corrections 4/18/2023 DANIEL YIP
Applicant returned to address corrections 12/29/2023 DANIEL YIP
Plan Check Approved 1/10/2024 DANIEL YIP
Issued 1/18/2024 APPLICANT
CofO in Progress 2/12/2026 LILIANA PORTILLO
Permit Finaled 2/13/2026 DEROLD HAUFF
CofO Issued 2/13/2026 DEROLD HAUFF
Permit Finaled 2/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/22/2023 TREVOR QUAN
Hydrant and Access approval Cleared 6/6/2023 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 6/16/2023 TREVOR QUAN
Sewer availability Cleared 6/16/2023 TREVOR QUAN
Frnt yard landscape/Water mgmt Cleared 6/21/2023 MAYELA VILLA
Opn space landscape/Water mgmt Cleared 6/21/2023 MAYELA VILLA
Low Impact Development (LID) Cleared 9/22/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 12/21/2023 TREVOR QUAN
GPI Written Notices Cleared 1/10/2024 DANIEL YIP
Grading Pre-Inspection Cleared 1/10/2024 DANIEL YIP

Contact Information

Contractor Bpc Development Inc; Lic. No.: 1059885-B       ,
Contractor Builder Point Construction; Lic. No.: 1059885-B       ,
Engineer Salto,, Alvaro; Lic. No.: NA83859       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/16/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 5/16/2024 Conditional Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 6/13/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Approved LILIANA PORTILLO
Special/Order Compliance 10/16/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 10/21/2024 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 10/28/2024 Approved BRENDAN MORELLI
PLUMBING-Rough 10/28/2024 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 10/30/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 10/30/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 11/19/2024 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 11/19/2024 Conditional Approval LILIANA PORTILLO
Verify Sprinkler Sign Off 11/19/2024 Approved LILIANA PORTILLO
Insulation 12/13/2024 No Access for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 12/13/2024 No Access for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 12/18/2024 Approved LILIANA PORTILLO
Green Building Rough 12/18/2024 Approved LILIANA PORTILLO
Insulation 12/18/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/18/2024 Partial Approval LILIANA PORTILLO
Drywall Nailing 12/31/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 2/21/2025 Approved LILIANA PORTILLO
Shower Pan 2/21/2025 Approved LILIANA PORTILLO
Underground Mechanical 5/1/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 6/26/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 6/26/2025 Corrections Issued LILIANA PORTILLO
HVAC-Rough 6/26/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 6/26/2025 Corrections Issued LILIANA PORTILLO
Verify Rec and Parks Fee Memo 7/25/2025 Approved JOSH MEISTER
ELECTRICAL-Final 10/17/2025 Corrections Issued LILIANA PORTILLO
Smoke Detectors 10/17/2025 Approved LILIANA PORTILLO
HVAC-Final 10/21/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 10/22/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV Approved LILIANA PORTILLO
ELECTRICAL-Final 10/27/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 11/7/2025 Corrections Issued LILIANA PORTILLO
Final 11/24/2025 Corrections Issued LILIANA PORTILLO
Gas Test 11/24/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/8/2025 Approved LILIANA PORTILLO
HVAC-Final 12/9/2025 Not Ready for Inspection DAVID WILLIAMS
HVAC-Final 12/11/2025 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 1/13/2026 Approved LILIANA PORTILLO
Final 1/13/2026 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 1/13/2026 Approved LILIANA PORTILLO
Green Building Final 1/13/2026 Approved LILIANA PORTILLO
Service/Power Release 1/13/2026 Approved LILIANA PORTILLO
Final 2/3/2026 Conditional Approval ALIZAH MAYAGOITIA
Service/Power Release 2/3/2026 Approved ALIZAH MAYAGOITIA
Final 2/11/2026 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 2/11/2026 Approved LILIANA PORTILLO