3265 N OAKDELL ROAD 91604
Certificate Information: 3265 N OAKDELL ROAD 91604
- Application / Permit
- 23010-10000-00985
- Plan Check / Job No.
- B23LA04105
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: (N) DETACHED ACCESSORY DWELLING UNIT PER LADBS STANDARD PLAN #5/HCD FOR FACTORY BUILT HOUSING. ALL PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g). NFPA-13D FIRE SPRINKLERS THRU-OUT
- Permit Issued
- Issued on 9/12/2023
- Issuing Office
- Current Status
- CofO Issued on 9/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2023 | OMAR GARNICA |
| Corrections Issued | 3/15/2023 | OMAR GARNICA |
| Applicant returned to address corrections | 9/6/2023 | OMAR GARNICA |
| Plan Check Approved | 9/11/2023 | OMAR GARNICA |
| Issued | 9/12/2023 | APPLICANT |
| CofO in Progress | 6/2/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 9/11/2025 | RUBEN SALAS |
| Permit Finaled | 9/11/2025 | RUBEN SALAS |
| CofO Issued | 9/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/10/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 4/13/2023 | ROMAN GUTIERREZ |
| Low Impact Development (LID) | Cleared | 7/11/2023 | TOMMY YIN |
| Specific Plan | Cleared | 8/28/2023 | JUDE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 9/7/2023 | ROMAN GUTIERREZ |
| Street Frontage | Cleared | 9/7/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Abodu Inc; Lic. No.: 1073522-B | , |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/6/2023 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 11/6/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 12/14/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Sewer | 12/14/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Underground Mechanical | 12/14/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 12/18/2023 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 12/19/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/28/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 12/28/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 12/28/2023 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/28/2023 | SGSOV Not Required | CHRISTOPHE COCHRAN |
| Service/Power Release | 12/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 12/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Final | 1/24/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 1/24/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/16/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |