142 E 84TH ST 1-12 90003
Certificate Information: 142 E 84TH ST 1-12 90003
- Application / Permit
- 23010-10000-00972
- Plan Check / Job No.
- B23LA04071
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3 STORY TYPE IIIA 12 UNITS (100% AFFORDABLE HOUSING, 2 UNITS EXTREMELY LOW INCOME AND 10 UNITS LOW INCOME) APARTMENT, TIER 2 TOC WITH BASE INCENTIVE (ED-1)
- Permit Issued
- Issued on 5/29/2024
- Issuing Office
- Current Status
- Issued on 5/29/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | MANUEL MONTUFAR |
| Assigned to Zoning Architect | 3/9/2023 | FRANCIS AHN |
| Corrections Issued | 3/23/2023 | MANUEL MONTUFAR |
| Quality Review Completed | 3/23/2023 | EUGENE BARBEAU |
| Plan Check Approved | 5/16/2024 | MANUEL MONTUFAR |
| Issued | 5/29/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2023 | CELINA MORENO |
| Permit | Cleared | 4/12/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2023 | CELINA MORENO |
| Sewer availability | Cleared | 8/9/2023 | CELINA MORENO |
| Trees in Parkway | Cleared | 8/21/2023 | ADALBERTO VERA |
| Low Impact Development (LID) | Cleared | 11/17/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/27/2023 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 1/8/2024 | JOE TAM |
| Opn space landscape/Water mgmt | Cleared | 1/8/2024 | JOE TAM |
| Density Bonus 12.22.A.31 | Cleared | 1/29/2024 | RICHARD TRUONG |
| SB8 RUD | Cleared | 1/29/2024 | RICHARD TRUONG |
| Hydrant and Access approval | Cleared | 2/6/2024 | LAVEON RIDER |
| Green Code | Cleared | 3/9/2024 | MANUEL MONTUFAR |
| Fire Marshal Fire Life Safety | Cleared | 3/19/2024 | RONILO MULAWIN |
| DAS Clearance | Cleared | 5/1/2024 | MANUEL MONTUFAR |
| Zoning Plan Check | Cleared | 5/7/2024 | FRANCIS AHN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
| Engineer | Pukkanasut,, Jirayus; Lic. No.: C73728 | 1424 ROLLING HILLS DR FULLERTON, CA 92835 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/5/2024 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 7/3/2024 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 7/26/2024 | Approved | DANIEL VARNUM |
| Deputy Wood Construction | 8/9/2024 | Conditional Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 8/9/2024 | Corrections Issued | RAFAEL ESPINOZA |
| Deputy Wood Construction | 8/19/2024 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Approved | LARRY ARNICK |
| Drywall Nailing | 9/10/2024 | Corrections Issued | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 9/13/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 9/13/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 9/17/2024 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 9/24/2024 | Corrections Issued | RAFAEL CORTES |
| Drywall Nailing | 11/27/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 11/27/2024 | Partial Approval | RAFAEL CORTES |
| Final | 12/2/2025 | Corrections Issued | JOEY BUCHANAN |
| Green Building Final | 12/2/2025 | Approved | JOEY BUCHANAN |
| Green Building Rough | 12/2/2025 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 12/2/2025 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 12/2/2025 | Approved | JOEY BUCHANAN |
| Verify Sprinkler Sign Off | 12/2/2025 | Approved | JOEY BUCHANAN |
| Final | 5/7/2026 | Conditional Approval | RAFAEL CORTES |